A kind of rapid construction device and construction method of flexible composite pipe
A flexible composite pipe and construction method technology, applied in pipeline laying and maintenance, pipes/pipe joints/pipe fittings, mechanical equipment, etc., can solve the problems of large manpower, low efficiency, and cost, so as to save labor, improve construction efficiency, The effect of shortening the construction time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0044] Aramid fiber reinforced PE-RT flexible composite pipe (specification DN100PN4MPa) rapid construction 2km, including the following steps:
[0045] (1) Line sweeping on the working surface: According to the specified width of the oilfield ground gathering and transportation pipeline installation, clean the pipeline passing through the ground of the lot, and the sweeping width is 6m, which meets the vehicle traffic and operation requirements;
[0046] (2) Excavate a foundation pit with a bottom size of 2m*2m and a depth of 1.2m at the starting point of pipeline installation and the end point of a single pipeline. This time, 4 pipes are shared, each 500m long, so a total of 5 foundation pits are excavated;
[0047] (3) Rapid construction device adjustment: adjust the excavation depth to 1.2m and the width to 0.5m;
[0048] (4) Rapid construction work: control the forward speed of the power vehicle and the unwinding speed of the pipe coil to 15km / h, and drive in one directio...
Embodiment 2
[0054] Polyester fiber reinforced PE-RT type flexible composite pipe (specification DN80PN2.5MPa) rapid construction 0.8km, including the following steps:
[0055] (1) Line sweeping on the working surface: According to the specified width of the oilfield ground gathering and transportation pipeline installation, clean the pipeline passing through the ground of the lot, and the sweeping width is 6m, which meets the vehicle traffic and operation requirements;
[0056] (2) Excavate a foundation pit with a bottom size of 2m*2m and a depth of 1.2m at the starting point of pipeline installation and the end point of a single pipeline. This time, the shared pipeline is 800 meters long, so a total of 2 foundation pits will be excavated;
[0057] (3) Rapid construction device adjustment: adjust the excavation depth to 0.5m and width to 0.4m;
[0058] (4) Rapid construction work: control the forward speed of the power vehicle and the unwinding speed of the pipe coil to 25km / h, and drive ...