Construction process of open sea fan foundation rock-socketed pile

A construction technology and fan foundation technology, which is applied in the direction of foundation structure engineering, foundation structure test, sheet pile wall, etc. The effect of horizontal resistance

Active Publication Date: 2016-11-16
CCCC THIRD HARBOR ENG +2
View PDF5 Cites 22 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Auxiliary steel pipe pile pulling and pile top cutting pile repair take a long time, and the cost is high, which is not economical. This structure is only suitable for the calm sea area of ​​the inner bay

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction process of open sea fan foundation rock-socketed pile
  • Construction process of open sea fan foundation rock-socketed pile
  • Construction process of open sea fan foundation rock-socketed pile

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0035] The present invention will be further described below in conjunction with accompanying drawing.

[0036] see Figure 1 to Figure 4 , the construction process of rock-socketed piles for offshore wind turbine foundations of the present invention includes steel pipe pile sinking, construction work platform erection, drilling, intermediate inspection, final hole, hole cleaning, hole measurement, placing steel cages, placing conduits, secondary Hole cleaning and underwater concrete pouring process.

[0037] When carrying out the steel pipe pile sinking process, a special piling ship is used to sink six steel pipe piles with a slope of 5:1 and uniformly distributed on a circular track curve with a diameter of 10m into the foundation by driving piles.

[0038] When erecting the construction operation platform, first use the steel pipe piles to construct the concrete layer of the bottom cover of the platform, and then build the working platform on the concrete layer of the botto...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction process of an open sea fan foundation rock-socketed pile. The construction process comprises the steps of pile sinking of a steel pipe pile, setting a construction operation platform, drilling, performing intermediate inspection, finishing a drilled hole, clearing the hole, measuring the hole, placing a steel reinforcement cage, placing a guide pipe, clearing the hole for the second time and performing underwater concrete pouring procedure. In the pile sinking procedure of the steel pipe pile, six steel pipe piles with the inclination of 5:1 which are uniformly distributed on the circular track curve are sunken into the foundation in the pile driving way by a special pile driving boat; in the setting procedure of the construction operation platform, the construction of a bearing platform bottoming concrete layer is performed and the construction operation platform is erected on the bearing platform bottoming concrete layer; the concrete of the bearing platform bottoming concrete layer is performed by the steel pipe piles; the construction operation platform is square and comprises an upper bailey frame, a lower bailey frame, a steel platform panel and a safety fence. According to the construction process, the construction efficiency of the pile socketing into rock can be improved, the horizontal resistance and the anti-shifting capability of the rock-embedded piles can be effectively improved, and the requirements of engineering structure design and construction are met.

Description

technical field [0001] The invention relates to a construction technology of a rock-socketed pile for an offshore fan foundation. Background technique [0002] For the construction of offshore wind turbines in open sea areas far away from the land and with a water depth of 16m to 19m, due to the constraints of natural conditions such as weather, tides, and waves, and in areas where tropical storms frequently occur, and the bearing and resistance of the wind turbine equipment to the foundation Pullout force and deformation have very high requirements, so the pile foundation diameter is required to be large and the depth of soil penetration is deep, so that the fan foundation can withstand the huge overturning moment of the fan and withstand the load of waves and water flow, and the construction schedule control is especially important. The essential. In the field of offshore wind farm foundation design, when the water depth is deep and the geological conditions are complex, ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D27/42E02D5/40E02D27/14E02D33/00E02D15/06
CPCE02D5/40E02D15/06E02D27/14E02D27/425E02D33/00E02D2250/0076
Inventor 郭新杰吴光辉丁友文陈思
Owner CCCC THIRD HARBOR ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products