Work plan making method of engineering construction

A work planning and engineering technology, applied in computing, instrumentation, data processing applications, etc., can solve the problems of heavy workload, repeated labor, poor uniformity, etc., to achieve the effect of fast process, reduce repeated labor, and save working time

Inactive Publication Date: 2016-12-07
RES INST OF ECONOMICS & TECH STATE GRID SHANDONG ELECTRIC POWER +1
View PDF0 Cites 6 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] With the development of the economy, the number of power grid constructions continues to increase. Due to the huge number of projects and different construction periods, the owner's project department has limited personnel, but each management s

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Work plan making method of engineering construction
  • Work plan making method of engineering construction

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0036] The specific implementation of the present invention will be described below in conjunction with the accompanying drawings. It should be understood that the implementation examples described here are only used to illustrate and explain the present invention, and are not intended to limit the present invention.

[0037] Such as figure 1 A method for preparing an engineering construction work plan is shown, and the method includes the following steps.

[0038] Step 1: Obtain the name of the project, the overall design data and the total construction period T. In fact, what is obtained is a plan, which includes the project name, the overall data of design and construction, and the total construction period required to complete.

[0039] Step 2: According to the project management standardization manual of the industry, divide the project into several divisional periods in sequence, such as figure 2 As shown, it is the division of the construction period of the project co...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a work plan making method of engineering construction. The method comprises the following steps: S1: obtaining the name, the integral design data and the total construction period T of engineering; S2: according to the engineering management standardization manual of an industry, dividing the engineering into a plurality of subordinate construction periods according to a sequential order; S3: according to the working type and the workload of each subordinate construction period, generating the working time interval [tn, Tn] of each subordinate construction period, wherein tn is the minimum time limit of each subordinate construction period, Tn is the maximum time limit of each subordinate construction period, and n is the time sequencing of the subordinate construction period in the whole total construction period; and S4: according to a certain ratio, compressing the maximum time limit Tn of each subordinate construction period until the sum of the maximum time limits after all subordinate construction periods are compressed is equal to the preset total construction period T. By use of the method, the standardization management manual of the project department of a power grid enterprise owner is taken as a basis, a reasonable construction period is automatically generated by means including construction period key points, compression functions and the like, and a workload is effectively reduced.

Description

technical field [0001] The invention relates to the field of power grid engineering, in particular to a method for preparing an engineering construction work plan. Background technique [0002] Production planning management (Product Planning Management) generally refers to the company's planning, organization and control of production activities. Production planning management in a narrow sense refers to the management of the basic production process of products, including production process organization, production capacity verification, production plan and production operation plan formulation and implementation, and production scheduling. The production planning management in a broad sense has a new development, which refers to the management of the company's production system, including all aspects of work closely related to the manufacture of products, that is, starting from the input of raw materials, equipment, manpower, capital, etc. Through the production conversi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): G06Q10/06G06Q50/06
CPCG06Q10/06316G06Q50/06
Inventor 张益曾军张利民明志舒朱毅姜海英郑磊张洪健赵斌李文杰
Owner RES INST OF ECONOMICS & TECH STATE GRID SHANDONG ELECTRIC POWER
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products