Installation Method of Steel Box Girder of Hybrid Continuous Rigid Frame Bridge

An installation method and technology of steel box girder, applied in the direction of bridges, bridge construction, bridge materials, etc., can solve the problems of high construction cost, safety, efficiency discount, etc., achieve significant economic effects, improve construction safety and construction efficiency. Effect

Active Publication Date: 2019-04-16
CHINA MAJOR BRIDGE ENERGINEERING
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

This construction method involves a large number of water operations, which greatly reduces the safety and efficiency of construction in sea areas where strong winds and waves occur, and the construction time is also subject to weather conditions; at the same time, large-tonnage construction vessels are required for transportation and hoisting. high construction cost

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Installation Method of Steel Box Girder of Hybrid Continuous Rigid Frame Bridge
  • Installation Method of Steel Box Girder of Hybrid Continuous Rigid Frame Bridge
  • Installation Method of Steel Box Girder of Hybrid Continuous Rigid Frame Bridge

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0027] The present invention will be described in further detail below in conjunction with the accompanying drawings.

[0028] The invention provides a method for installing a steel box girder of a continuous rigid frame bridge with mixed girders. The method includes the following steps:

[0029] S1. Divide the steel box girder 1 to be installed into multiple steel box girder segments that can be assembled, and construct the first concrete beam 2 and the second concrete beam 3 respectively on two adjacent piers, and construct the first concrete beam 2 and the second concrete beam 3 on the first concrete One end of the beam 2 and the second concrete beam 3 used to connect the steel box girder 1 is used for the construction of the hybrid joint 4;

[0030] In the present invention, the steel box girder 1 is divided into 4 steel box girder segments that can be assembled, and the number of steel box girder segments can be reasonably set according to the actual situation, such as th...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an installation method of a steel box girder of a hybrid beam continuous rigid frame bridge and relates to the field of steel box girder installation. The method comprises thefollowing steps: the steel box girder to be installed is divided into a plurality of assemblyable steel box girder sections, and the construction of a first concrete girder, a second concrete girder and hybrid joints is performed; two deck cranes are hoisted onto the first concrete girder and the second concrete girder separately, and all the steel box girder sections are hoisted onto the first concrete girder; the steel box girder sections are assembled into the steel box girder; a sliding device is laid on the first concrete girder, and a nose girder is additionally arranged on the end, nearthe second concrete girder, of the steel box girder; the steel box girder is pushed until the two ends of the steel box girder are aligned with the hybrid joints on the first and second concrete girders separately; and the nose girder and the sliding device are removed, the steel box girder is lifted by using the deck cranes, the steel box girder is lowered, the steel box girder is placed betweenthe two hybrid joints, welding is performed, and operation is completed. The installation method can reduce the cost, improve the construction efficiency and ensure the safety.

Description

technical field [0001] The invention relates to the field of steel box girder installation, in particular to a method for installing a steel box girder of a continuous rigid frame bridge with mixed girders. Background technique [0002] Hybrid beam generally refers to the main beam consisting of two forms of concrete beam and steel box girder. The main girder of existing long-span continuous rigid frame bridges often adopts the form of hybrid beams, that is, the fulcrum and certain areas on both sides adopt the form of concrete beams, and the mid-span area of ​​the main span adopts the form of steel box girders. [0003] In the existing hybrid girder continuous rigid frame bridge, the construction method of the mid-span steel box girder mainly adopts the overall hoisting method of large segments. This construction method needs to use a large-tonnage transport barge to transport the steel box girder, and a large-tonnage bridge deck crane or a large floating crane is required...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E01D21/00E01D2/04E01D101/30
CPCE01D2/04E01D21/00E01D2101/30
Inventor 肖海珠张建强付岚岚郑清刚邱峰谭国宏龚俊廖贵星郭子俊孙立山李少骏何东升李华云苑仁安邱远喜
Owner CHINA MAJOR BRIDGE ENERGINEERING