A foundation pit support structure and construction method
A technology of foundation pit support and construction method, which is applied in basic structure engineering, excavation, construction, etc., can solve problems such as unsafety, anchor bar detachment, etc., and achieve the effect of high support capacity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0046] This embodiment provides a foundation pit support structure, the foundation pit support structure includes a slope protection unit 100 arranged on the inner wall of the foundation pit, and at least Two groups of anchoring units 200, and several load-bearing units 300 connected to the slope protection unit 100 and the anchoring unit 200 in turn; each group of anchoring units 200 is a ring structure arranged around the foundation pit, and multiple groups of anchoring units 200 are arranged at intervals to form A number of annular rings surrounding the foundation pit;
[0047]The slope protection unit 100 includes a soil nail wall 101 attached to the inner wall of the foundation pit, the anchor unit 200 includes a poured concrete structure arranged in the soil body along the vertical direction, and the bearing unit 300 includes a bearing unit 301 for bearing tensile stress And a pressure bearing unit 302 for bearing compressive stress.
[0048] The principle of the presen...
Embodiment 2
[0054] This embodiment provides a construction method of a foundation pit support structure in Embodiment 1, see figure 1 and figure 2 , the method includes the following steps:
[0055] S100. Excavate anchor pits, and excavate at least two sets of anchor pits sequentially along the foundation pit to the direction away from the foundation pit; the distance between the anchor pits depends on the fluidity of the soil. Generally, the soil flows The greater the resistance, the greater the distance between the anchoring pits, and the greater the number of anchoring pits, the larger the area surrounded by the outermost anchoring pits as a whole.
[0056] S200, setting the load-bearing unit 300, drilling horizontally arranged accommodating holes for piercing the pressure-bearing unit 302 and the tension-bearing unit 301 respectively along the foundation pit to the direction away from the foundation pit, for piercing the pressure-bearing unit 302 The aperture of the accommodating h...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More - R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com