Steel beam, concrete ring beam and concrete floor structure integrated construction method

A technology of concrete and steel beams, which is applied in the direction of building construction, construction, and building materials processing, etc., which can solve the problems of high hoisting accuracy requirements, many high-altitude operations, and complicated procedures, so as to avoid unsafe factors and reduce turnover materials The consumption and the effect of shortening the construction period

Inactive Publication Date: 2018-11-06
QINGDAO BOHAI CONSTR GROUP +1
View PDF2 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In the conventional construction process, it is often used to bury the embedded parts first to pour the reinforced concrete ring beam, then install the steel beam, and then pour the roof concrete. Many, complex procedures, long construction period

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Steel beam, concrete ring beam and concrete floor structure integrated construction method
  • Steel beam, concrete ring beam and concrete floor structure integrated construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0068] The integrated construction method of steel beam, concrete ring beam, and concrete floor structure provided in this embodiment includes the following steps:

[0069] (1) Bolting of embedded parts

[0070] The embedded parts are bolted into the ground before hoisting. The high-precision bolting method ensures the overall construction quality of the later steel beams. The specific operations are as follows:

[0071] 1 Bolting and tightening: do initial and final tightening when bolting. In order to reduce the difference between the pretension of the high-strength bolts that are tightened first and tightened later, the tightening must be divided into two steps: initial tightening and final tightening. For large nodes with a large number of bolts, a re-tightening process and re-tightening torque are required. It is still equal to the initial tightening torque to ensure that the bolts reach the design value.

[0072] 2 Tightening inspection: The torque wrench used for tightening th...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a steel beam, concrete ring beam and concrete floor structure integrated construction method. The steel beam, concrete ring beam and concrete floor structure integrated construction method comprises the following steps that (1), built-in fittings are connected in a bolted mode; (2), a full-hall frame is erected; (3), a steel beam is hoisted and installed and fixed; (4), beam main steel bars and stirrups are arranged in advance and positions are reserved; (5), formwork erecting and steel bar binding are performed; and (6), concrete pouring and maintenance is performed. The built-in fittings (anchorage parts) and the steel beam are welded and connected in a bolted mode in a factory and then lifted to the designed elevation to be subjected to overall pouring with concrete ring beam slabs and columns though a deepening design of the steel structure, the positioning accuracy of the steel beam is improved, the number of concrete pouring is reduced, and the construction period is saved. According to the construction method, the built-in fittings and the steel beam are connected in the bolted mode on the ground in advance, the aloft work is reduced, and safety is improved. The integrated construction method specifies the steel bar binding sequence at the position of column and ring beam caused by the pre-installation of the steel beam, and can meet the quality requirements of steel bar binding.

Description

Technical field [0001] The invention relates to an integrated construction method of steel beam, concrete ring beam and concrete floor structure, belonging to the technical field of building construction. Background technique [0002] With the development of economy, the structural situation of buildings is becoming more and more diverse. In the process of large-scale stadium construction, in order to improve the space utilization rate and achieve beautiful and practical effects, it is more common to use steel beams instead of traditional concrete beams. In the conventional construction process, the method of burying the embedded parts to pour the reinforced concrete ring beam, then installing the steel beam, and then pouring the roof concrete is often adopted. Although this process is more common, it requires high precision for hoisting and high-altitude operations. More, complicated procedures and longer construction period. Summary of the invention [0003] The technical probl...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E04G21/00
CPCE04G21/00
Inventor 王霄鹏杨旭王竹林毕明强
Owner QINGDAO BOHAI CONSTR GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products