Steel foundation turnover method for super high-rise buildings with tower cranes
A super-high-rise and basic technology, applied in the direction of cranes, etc., can solve problems that affect the construction progress of the site, tower cranes cannot perform hoisting operations, and multiple construction joints
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0032] The present invention will be further described below in conjunction with the drawings and embodiments:
[0033] Such as Figure 1-8 As shown, a method for turning over the steel foundation of a tower crane attached to a super high-rise building is characterized by including the following steps:
[0034] Step a: Design a steel drawer frame. The steel drawer frame A is used to temporarily store the bottom one of the tower crane steel foundation B attached to it temporarily. The steel drawer frame is fixed on the structural floor 1. The steel drawer frame A includes a steel stand 2, in which the number of the steel stand 2 is three, and the three steel stands 2 are arranged side by side. Two adjacent steel stands 2 are fixedly connected by a set of beams 3, and the beam 3 between the two adjacent steel stands 2 supports the lowest steel foundation B for the tower crane.
[0035] The steel truss 2 includes four trusses. Two columns 4 of each truss are arranged side by side, and...