Cooling device and cooling method for shield tunnel construction
A shield tunnel and cooling device technology, which is applied in mine/tunnel ventilation, earthwork drilling, mining equipment, etc. It can solve the problems of high temperature and stuffy feeling in tunnels, reduce the ambient temperature, ensure safety, and protect construction personnel safe effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] This embodiment provides a cooling device for shield tunnel construction;
[0029] Such as figure 1 , The cooling device for shield tunnel construction in this embodiment includes a refrigeration system and an air cooling system arranged in the tunnel, and a shield circulating water system arranged outside the tunnel; the refrigeration system is connected to the air cooling system for Provide a cold source for the air cooling system; the air cooling system performs cold and heat exchange with the natural wind sent in from the ground to cool the natural wind. The cooled natural wind is sent to the construction area through the shield fan, thereby reducing The temperature of the construction area; the shield circulating water system is connected to the refrigeration system, and is used to dissipate heat and reduce the temperature of the refrigeration system to ensure the normal operation of the refrigeration system.
[0030] The invention provides a cold source for the air co...
Embodiment 2
[0036] This embodiment provides a cooling method for shield tunnel construction;
[0037] Such as figure 1 , The cooling method of shield tunnel construction in this embodiment includes the following steps:
[0038] a. According to the size of the cooling equipment in the refrigeration system and the air cooling system, measure the tunnel space on site, and add a 10m trolley at the tail of the shield machine to connect with the original shield machine trolley;
[0039] b. Install the refrigeration system on the newly added trolley, that is, install the refrigeration host with a size of 1.2×3m on the left aisle plate of the newly added trolley, and use a DN100 water pipe to connect the circulating water to the refrigeration host; and at the outlet of the refrigeration host Install heat preservation water tank 10 and internal circulation water pump 11;
[0040] c. Install an air cooling system between the newly added trolley and the top of the tunnel. The air cooling system is located ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com