An Optimal Control Method of Sectional Power Flow Based on n-1 Static Safety Constraints
A cross-section flow optimization control technology, which is applied to AC networks with the same frequency from different sources, AC network circuits, single-network parallel feeding arrangements, etc., can solve the cross-section flow without considering the load distribution change of the receiving end network on the transmission section Influence, inability to realize large-scale directional control of cross-section power flow, complex power flow tracking calculations, etc., to achieve the effect of improving the adjustment effect, fast calculation speed, and good adjustment effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0057] An optimal control method for section power flow based on N-1 static security constraints, please refer to figure 1 , including the following steps:
[0058] S1: Collect the operation data of the power grid in a certain area for power flow calculation;
[0059] S2: On the basis of power flow calculation, calculate the variance sensitivity of each generator set to the power flow section respectively, and according to the variance sensitivity dσ of the generator set 2 / dP gk The absolute value of to select the generating set with the largest variance sensitivity;
[0060]S3: Define the calculation parameters of the genetic algorithm, the number of iterations, and randomly generate the variable population of [generator unit output, load shedding];
[0061] S4: Update the operation mode of the transmission section, even if a certain line of the section is out of operation, calculate the power flow under the N-1 operation mode;
[0062] S5: Use the GAGenAdjust function i...
Embodiment 2
[0101] like figure 2 , the number of power grid nodes in a certain area is 31, of which 1, 2, 3, 4, and 31 are generator sets, and the power flow section is 6 transmission branches, which are 3 branches of nodes 7-5 and three branches of nodes 9-6 branch road. The 7-5 branch is three parallel transmission lines. In the early stage of power grid planning, the 7-5 branch has only two lines. Later, due to the power supply demand, an additional line is added, so the parameters of the later installed line are different from those of the previous two lines. In actual operation, the transmission power of the three transmission lines is different, and it is easy to overload a certain line or two lines, so the power flow control is carried out on this section.
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 


