Construction technology of pile holder for wind power installation platform

A technology for installing platforms and pile holders, which is applied in construction, sheet pile walls, infrastructure engineering, etc., can solve the problem of small deviation correction range, etc., and achieve the effect of stable movement of the pile body and increasing the range of deviation correction.

Active Publication Date: 2020-08-28
NANTONG ZHENHUA HEAVY EQUIP MFG
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

When such a structural form is used to correct the deviation of the pile, the range of the deviation correction is determined according to the stroke range of the two side thrust cylinders, and the side thrust cylinders are installed on the side close to the clamp arm, which leads to the entire The range of deviation correction is relatively small. In addition, in the process of deviation correction, the side thrust cylinder is used to drive the telescopic arm to swing as a whole, which causes the two clamp arms to clamp the pile for deviation correction. The swing direction of the pile must be consistent, that is, the movement track of the pile is certain, and the corresponding range of correction for the pile is further limited.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction technology of pile holder for wind power installation platform
  • Construction technology of pile holder for wind power installation platform
  • Construction technology of pile holder for wind power installation platform

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0053] The following examples can enable those skilled in the art to understand the present invention more comprehensively, but the present invention is not limited to the scope of the described examples.

[0054] Such as Figure 1-Figure 11 A pile holder for a wind power installation platform shown, including

[0055] A chassis 1, the chassis 1 is driven by a traversing mechanism to realize lateral movement in the horizontal direction, and driven by a longitudinal movement mechanism to realize longitudinal movement in the horizontal direction.

[0056] Such as figure 2 , image 3 As can be seen from the schematic diagram shown, the traversing mechanism includes a pair of traversing guide rails 2 distributed side by side and extending laterally. The traversing guide rails 2 are in the shape of an I-shape. The shifting wheel assembly includes traverse wheels 3 respectively installed on both sides of the traverse guide rail 2 and reciprocatingly rolling along the extension d...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a wind power installation platform pile-holding device construction process. The production of a box type arm claw, the production of a supporting truss, the production of a locking device, and the production of a traverse movement mechanism and vertical movement mechanism are firstly performed, after the above assemblies are produced, the pre-assembly of a clamping arm assembly is firstly performed, then a chassis is arranged on the upper ends of the traverse movement mechanism and vertical movement mechanism, and then the assembled supporting truss and clamping arm assembly are welded on the chassis to complete the construction of a pile-holding device. The wind power installation platform pile-holding device construction process has the advantages that the pile-holding device is constructed by the construction process, and the traverse movement mechanism and the vertical movement mechanism are established, thereby achieving the traverse and vertical movementof the chassis; the maximum correcting force can reach 100 tons; the joint operation of a swinging mechanism is utilized, thereby achieving the correction in any direction, and greatly increasing therange of the correction.

Description

technical field [0001] The present invention relates to a construction process of a pile holding device, in particular to a construction process of the above-mentioned pile holding device for a wind power installation platform. Background technique [0002] The use of wind power to generate electricity is very environmentally friendly and has a huge wind energy reserve, so it is increasingly valued by countries all over the world. my country is rich in wind energy resources, and the wind energy reserves that can be developed and utilized are about 1 billion kW, among which, the wind energy reserves that can be developed and utilized at sea are about 750 million kW. For the further development and utilization of this clean energy. The National Energy Administration requires that we do a good job in the development and construction of offshore wind power and accelerate the development of offshore wind power. Therefore, offshore wind power installation ships have become the m...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D13/04
CPCE02D13/04
Inventor 吴正峰沈鹏鹏季秋兵于洪贞林海桥