Segmented prefabrication process with bolted members
A connecting rod and bolt technology, which is applied to the prefabrication process of slicing in modules and the field of slicing prefabrication process, can solve the problems of waste of resources, easy repair of bolted connecting rods, failure of normal installation and prefabrication of bolted connecting rods, etc., to avoid The effect of waste of resources, solving the problem of prefabrication installation accuracy, and improving the efficiency of prefabrication
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0046] Such as Figure 1-Figure 13 Shown, the present invention adopts following steps:
[0047] The first step: if figure 1 As shown, after the main beam 1 is cut according to the actual size, the first main beam stiffener plate 12 is installed on the flange where bolt holes need to be opened on the inner side of the shaped steel by welding; then, the second bolt hole needs to be opened outside the shaped steel The second main beam stiffener plate 13 is placed in the installation position; then the first main beam stiffener plate 12 and the second main beam stiffener plate 13 are drilled together with the main beam 1 flange, and the second main beam stiffener plate 13 Use four temporary ordinary bolts to install and fix on the main beam 1 flange, and apply 100% torque;
[0048] The second step: if figure 2 As shown, several main stiffeners 11 arranged on the main girder 1 are prefabricated into a small whole; since the main stiffeners 11 are spliced by several steel pla...