The construction method used for anti-burst of ultra-deep foundation pit
A construction method and technology for deep foundation pits, which can be used in infrastructure engineering, excavation, construction, etc., and can solve problems such as hidden water inrush hidden dangers
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific Embodiment approach
[0086] Taking the clearance wells on both sides of the rail transit station as an example, the foundation pit to be constructed is the clearance well. Since the surrounding buildings of the foundation pit are stations, the requirements for ground settlement are extremely high, and the settlement range should not be greater than 2mm and 5mm. , the top elevation of the confined water layer in the construction area is -23.92 ~ -26.31m, and the deepest excavation of the foundation pit is 23.6m, which is very close to the confined water layer. Only when it reaches 13.6m can the safety requirements of foundation pit excavation be met. This project needs to excavate four foundation pits;
[0087] Calculate the bottom elevation of the waterproof reinforcement layer according to ∑h·γs≥Fs·γw·H, the thickness of the water insulation reinforcement layer is 10m, and the thickness of the pressure reduction reinforcement layer is 3m. In the calculation, it is necessary to take into account th...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com