Project progress monitoring method and system

A monitoring system and engineering technology, applied in the direction of data processing applications, instruments, calculations, etc., can solve the problems of progress control lag, lack of detailed data support, weak pertinence of solutions, etc., to achieve the effect of meeting actual needs

Pending Publication Date: 2020-02-28
SHANGHAI CONSTR NO 5 GRP CO LTD
View PDF9 Cites 14 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] 1. The progress monitoring can only be compared with the schedule after the on-site inspection, and only rely on manpower for monitoring
[0004] 2. Traditional schedule control often has very serious hysteresis. When a large error occurs, the cost of remedial measures required is very high
[0005] 3. Without detailed data support, it is difficult to find the progress lag problem, and the solution measures are weak

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Project progress monitoring method and system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0028] In order to make the above objects, features and advantages of the present invention more comprehensible, the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0029] Such as figure 1 As shown, the present invention provides a method for project progress monitoring, comprising:

[0030] Step S1, establishing a BIM model of the project;

[0031] Step S2, associating the BIM model with the construction schedule of the project to form the planned progress data in the project three-dimensional progress monitoring platform;

[0032] Step S3, obtaining the actual amount of materials used in each construction part of the project, and connecting the actual amount of materials used in each construction part of the project to the three-dimensional progress monitoring platform of the project to generate actual progress status data;

[0033] In step S4, the project three-dimensional progress monit...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a project progress monitoring method and system. The method comprises the following steps: establishing a BIM model of a project; associating the BIM model with a construction progress plan of the project to form planned progress data in a project three-dimensional progress monitoring platform; acquiring the actual material consumption of each construction part of the project, and accessing the actual material consumption of each construction part of the project to the project three-dimensional progress monitoring platform to generate actual progress condition data; andthe project three-dimensional progress monitoring platform comparing the planned progress data with actual progress condition data to obtain a progress deviation result. The engineering three-dimensional progress monitoring platform can serve project participants to better perform project management through application developed by technologies such as the Internet and the cloud technology on thebasis of the background of the informatization era, and meanwhile, the actual requirements of enterprise levels for project management and control are met.

Description

technical field [0001] The invention relates to a project progress monitoring method and system. Background technique [0002] Usually, the traditional schedule control mode in project management has the following problems: [0003] 1. The progress monitoring can only be compared with the schedule after the on-site inspection, and only rely on manpower for monitoring. [0004] 2. Traditional schedule control often has a very serious hysteresis. When a large error occurs, the required remedial measures are very costly. [0005] 3. Without detailed data support, it is difficult to find the progress lag problem, and the solution measures are not targeted. Contents of the invention [0006] The object of the present invention is to provide a project progress monitoring method and system. [0007] In order to solve the above problems, the present invention provides a project progress monitoring method, comprising: [0008] Build the BIM model of the project; [0009] Assoc...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/10G06Q50/08
CPCG06Q10/103G06Q50/08
Inventor 王斌潘峰杨群荣毛子成王孙骏
Owner SHANGHAI CONSTR NO 5 GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products