Process for protecting existing piers on two sides in tunnel construction
A technology for tunnel construction and bridge piers, which is applied in the direction of bridges, bridge construction, bridge parts, etc. It can solve the problems of easy leakage of foundation pits, unbalanced stress on structural pile foundations, and untimely pouring, so as to prevent deformation and leakage of foundation pits , increase the overall stability, increase the effect of its own stiffness
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0037] Refer to attached figure 1 As shown, in this embodiment, the main protection process steps are briefly introduced.
[0038] In this embodiment, a protection process for existing bridge piers on both sides during tunnel construction includes several bridge piers. When several bridge piers are set, the proposed tunnel is used as the axis, and the bridge piers on both sides of the proposed tunnel are the middle piers. The piers on the outside of the non-adjacent planned tunnel are end piers; the protection process for several of the piers includes the following steps:
[0039]The construction of S1 preliminary enclosure: adopt the enclosure pile of different grades to carry out initial enclosure respectively to intermediate pier and end pier; The intensity of described end pier enclosure pile is less than the grade of described intermediate pier enclosure pile;
[0040] Construction of S2 strengthened enclosure: after the preliminary enclosure, the composite pile and the ...
Embodiment 2
[0048] In this embodiment, the construction of the primary enclosure in the core construction steps is described in detail.
[0049] Specifically, with regard to the construction of the preliminary enclosure in step S1, it is specifically: through the piling process, the construction of the initial enclosure structure for the middle pier and the end pier is carried out by using interlocking steel pipe piles and steel sheet piles respectively.
[0050] In this embodiment, steel sheet piles are used for enclosure at the end where the requirements for bearing strength are small and the degree of interference is small, while for the middle position with high bearing strength and high degree of interference, locking steel pipe piles are used for enclosure , Compared with piling with uniform materials, it saves materials and the selection of piling is more humanized and rational. The steel sheet pile is preferably OZ20A type steel sheet pile to reduce the unbalanced earth pressure w...
Embodiment 3
[0063] In this embodiment, steps 2-3 are further described in detail.
[0064] Specifically, the construction of step S2 to strengthen the enclosure is: to form a cast-in-place pile by drilling and pouring in the locked steel pipe pile near the side of the tunnel to form a composite pile of the locked pile and the cast-in-place pile, and to form a composite pile on the top of the composite pile. It is joined together with concrete crown beams to form a reinforced enclosure.
[0065] In this embodiment, the cast-in-situ pile formed by continuing drilling and pouring in the locked steel pipe pile increases the strength and rigidity of the locked steel pipe pile; when the tunnel foundation pit is excavated, the foundation soil is prone to lateral displacement, and the pile The foundation and abutment must bear additional bending moment and deformation. The setting of composite piles can increase the overall stability of the pile foundation and foundation.
[0066] Further, the ...