Oil-gas well casing pipe liquid resin leaking stoppage squeezing tool and construction technology
A liquid resin, oil and gas well technology, applied in wellbore/well components, earthwork drilling, sealing/packing, etc., can solve the long-term rubber plug drilling and grinding time-consuming and laborious, the liquid plugging agent is expensive, and the pipe string is tripped. The problem of many times, etc., achieves the effect of simple and easy construction process, reducing the cost and labor intensity of tripping and drilling, and reducing the cost of tripping and drilling.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0053] Zhen* Well was put into production on October 4, 2010, with an initial daily liquid production of 4.86m3, daily oil production of 3.15t, water content of 22.8%, dynamic liquid level of 1309m, and salt content of 71309mg / L; The liquid level is 259m, and the salt content is 23380mg / L. The analysis shows that the casing is damaged. Decided to do chemical plugging.
[0054] (1) Pull out the pipe string from the original well.
[0055] (2) Through the well.
[0056] Specifically: lower the Φ118mm×1.5m through well gauge, and lead to the bottom of the artificial well.
[0057] (3) Find leaks.
[0058] Specifically, the packer is used, and the whole well section is tested for leakage, and the location of the leakage point is determined to be 1608m.
[0059] (4) Tool lamination.
[0060] Specifically: use low-pressure polyethylene tape to wrap the tool string, with a thickness of 1.5mm, tighten the film tape, and the width of the blank holder is 12mm. Grow 20cm and stuff ...
Embodiment 2
[0075] Huan* Well was put into production on March 6, 2012, with an initial daily oil production of 2.86t, water cut of 25.3%, dynamic liquid level of 1433m, and salt content of 72,415mg / L; The salt was 21089mg / L, and the analysis indicated that the casing was damaged. Decided to do chemical plugging.
[0076] (1) Pull out the pipe string from the original well.
[0077] (2) Through the well.
[0078] Specifically: lower the Φ118mm×1.5m through well gauge, and lead to the bottom of the artificial well.
[0079] (3) Find leaks.
[0080] Specifically, the packer is used, and the whole well section is tested for leakage, and the location of the leakage point is determined to be 1608m.
[0081] (4) Tool lamination.
[0082] Specifically: use low-pressure polyvinyl chloride tape to wrap the tool string, with a thickness of 1.2mm, tighten the film tape, and the width of the blank holder is 15mm. The tool string covers the tool surface from the seat sealing tool to the coating o...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com