Site construction lofting device for house decoration and using method thereof
A technology for on-site construction and housing, applied in the field of lofting, can solve the problems of high risk factor, low lofting efficiency, climbing operations, etc., and achieve the effects of high safety, high lofting efficiency, and low error rate
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0033] Refer to attached Image 6 , for the convenience of explanation, a plane coordinate system composed of Y and Z is now defined, Y is the abscissa, positive to the left, Z is the ordinate, positive to the upward, and the following values are involved in the calculation in mm:
[0034] In this preferred embodiment, the distance from the left wall on the wall is Y 1 , Z from the ground 1 Stake out a line with a height of Z for the starting point 2 vertical line, the following steps are required:
[0035] A: Push the L-shaped trolley 1 so that its forward direction is roughly perpendicular to the staked-out wall. At this time, check the measurement data of the rangefinder through the touch screen 92. The distance measured by the left rangefinder 52 from the left wall is Y 0 , the distance measured by the lower rangefinder 51 from the ground is Z 0 , the distance measured by the front range finder 53 from the front wall is X 0 , the single-chip microcomputer 91 receive...
Embodiment 2
[0039] Refer to attached Figure 7 , for the convenience of explanation, a plane coordinate system consisting of X and Y is now defined, X is the abscissa, positive is forward, Y is vertical, positive is left, the following values are involved in the calculation in mm: