A hot dry rock and regional technology, applied in drilling equipment and methods, construction, earthwork drilling and mining, etc., can solve the problems of high cost of hydraulic fracturing, earthquakes, small heat transfer area of high-permeability fractures, etc., to achieve fracturing Wide range, good cracking effect and long service life
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0019] The present invention will be further described below.
[0020] Such as figure 1 with figure 2 Shown, concrete steps of the present invention are:
[0021] A. First delineate the hot dry rock development area from the ground, and then carry out geological exploration to obtain the maximum depth and location of the upper surface of the hot dry rock 4 below the development area and the ground, and the location directly above the hot dry rock 4 with the maximum depth The ground is determined as the construction location of injection well 1;
[0022] B. Drill the injection well 1 downward from the ground at the determined construction position, firstly make the depth of the injection well 1 reach the maximum depth of the hot dry rock 4 obtained by exploration, and then use temperature measuring equipment to measure the temperature of the rock mass at this depth, If the temperature of the rock mass does not exceed 200°C, the injection well 1 is continuously drilled until...