Subway open cut section prefabricated box culvert overlapping structure and construction method thereof
A construction method and technology for box culverts, which are applied in infrastructure engineering, excavation, underwater structures, etc., can solve the problems of difficult to guarantee the quality of bored piles, time-consuming construction period for waiting age strength, and unfavorable sustainable development. , to achieve the effect of improving industrialization efficiency and construction speed, avoiding maintenance time and saving project cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0039] In a typical implementation of the present disclosure, such as Figure 1-Figure 5 As shown, a superimposed structure of prefabricated box culverts in the open cut section of the subway is proposed.
[0040] It mainly includes box culverts and prefabricated piles. The prefabricated piles are distributed on both sides of the box culvert. Each side of the box culvert is matched with multiple prefabricated piles arranged at intervals. protection structure, and the box culvert is the main structure of the interval;
[0041] In this embodiment, the box culvert is a prefabricated rectangular box culvert structure, and the prefabricated piles are prefabricated square piles; Rotary grouting pile 3, the two interlock to form a continuous enclosure structure;
[0042] The shallow-buried section structure adopts prefabricated square piles and prefabricated rectangular box culvert components to realize industrialization, industrialization, and refinement, and overcome the traditio...
Embodiment 2
[0074] In another typical implementation of the present disclosure, such as Figure 1-Figure 5 As shown, a construction method of prefabricated box culvert superimposed structure in open cut section of subway is proposed.
[0075] Include the following steps:
[0076] Before the construction of prefabricated piles, carry out site leveling and measurement and positioning, drill holes and inject cement and mud into the wall, and position the prefabricated piles at the designed position;
[0077] According to the construction position, the prefabricated piles are placed in the design position, and the triple tube high-pressure rotary spraying is used between the prefabricated piles to make the high-pressure rotary spraying pile water-stop curtain;
[0078] Excavate the shallow buried section to the bottom elevation of the crown beam, apply concrete slope protection, and then construct the crown beam;
[0079] Carry out excavation step by step until the design elevation of the b...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com