High-water-content soft soil dewatering excavation integral trenching pipeline construction method

A high water content, pipeline construction technology, applied in the direction of excavation, pipeline laying and maintenance, soil protection, etc., can solve the problems of cofferdam deformation, low safety, low bearing capacity, etc., achieve stable and reliable support, and improve overall performance , Improve the effect of sealing performance

Active Publication Date: 2021-03-16
浙江世润建创科技发展有限公司
View PDF8 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] During the construction of pipelines in soft soil with high water content in river gushing areas, due to the high water level of the river, the natural water level during the construction period is higher than the elevation of the top surface of the trench, so it is often used to fill cofferdams on both sides of the trench, and then carry out Excavation and pipeline trenching construction operations; however, due to the high groundwater level, it still has a greater impact on trench excavation and pipeline trenching operations
Since the river bed is soft soil with high water content, the bearing capacity is low, resulting in deformation or collapse of the filled cofferdam
Large-scale construction machinery cannot enter the construction site, so the pipeline cannot be spliced ​​as a whole before being placed in the trench.
Due to the limited working space in the groove, the sealing performance of the joints and the axis accuracy of the pipeline cannot be effectively guaranteed, which affects the construction quality of the pipeline, and the splicing operation in the pipeline groove increases the risk of the operators and reduces the safety.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • High-water-content soft soil dewatering excavation integral trenching pipeline construction method
  • High-water-content soft soil dewatering excavation integral trenching pipeline construction method
  • High-water-content soft soil dewatering excavation integral trenching pipeline construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0036] The present invention will be further described below in conjunction with the examples. The description of the following examples is provided only to aid the understanding of the present invention. It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, some improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the protection scope of the claims of the present invention.

[0037] As an embodiment, the construction method for excavating integral trench pipelines in soft soil with high water content for precipitation includes the following construction steps:

[0038] 1) For the construction of the cofferdam dewatering structure, the pile-type downwater pipe 11 is inserted into the soil body on both sides of the ditch 87 to be excavated, and the top of the pile-type downwater pipe 11 is connected with the water collecting pipe 14; Pa...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a high-water-content soft soil dewatering excavation integral trenching pipeline construction method. The method comprises the following steps that 1) a cofferdam dewatering structure is constructed; 2) water in gunny bag cofferdams is pumped out, the surface of a riverbed is exposed, and temporary drainage blind ditches are constructed on the riverbed surfaces on the twosides of a trench to be excavated; 3) a steel sheet pile enclosure is inserted on the surface of the riverbed on the inner sides of the gunny bag cofferdams; 4) ramp slides are arranged on the gunny bag cofferdams on the two sides; 5) after the trench in the steel sheet pile enclosure is dug to a specified elevation, the adjustable easily-disassembled support is disassembled; 6) a material box isplaced on a filler moving and conveying frame; 7) a pipeline is placed on a pipeline moving and conveying frame; and 8) the material box slides to the top surface of the trench by using the filler moving and conveying frame. The method has the beneficial effects that the pipeline is lengthened on the pipeline moving and conveying frame, slides to the top face of the trench through the slides and then is integrally lifted through a sliding lifting support; the problem of transportation of the pipeline in the cofferdam is solved; and meanwhile, the pipeline integrally descends to the trench , and the sealing performance of a pipeline joint is improved.

Description

technical field [0001] The invention relates to the construction of high-water-content soft soil pipelines in river gushing areas, in particular to a construction method for excavating integrated trench pipelines in high-water-content soft soil for rainfall excavation. Background technique [0002] During the construction of pipelines in soft soil with high water content in river gushing areas, due to the high water level of the river, the natural water level during the construction period is higher than the elevation of the top surface of the trench, so it is often used to fill cofferdams on both sides of the trench, and then carry out Excavation and pipeline trenching construction operations; however, due to the high groundwater level, it still has a greater impact on trench excavation and pipeline trenching operations. Since the riverbed is soft soil with high water content and low bearing capacity, the filled cofferdams are deformed or collapsed. Large-scale constructio...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D19/04E02D5/04E02D17/06E02D17/08E02D3/10F16L1/028
CPCE02D3/10E02D5/04E02D17/06E02D17/08E02D19/04F16L1/028
Inventor 王新泉
Owner 浙江世润建创科技发展有限公司