Reinforcing method for shield underneath passing through underground street crossing channel

A technology for street crossing and shield tunneling, which is applied to underground chambers, tunnels, tunnel linings, etc. It can solve the problems that the safety of existing underground street crossing shield machines cannot be guaranteed, and achieve good pre-reinforcement effects, dry shrinkage, and anti-carbonization good sex effect

Inactive Publication Date: 2021-03-26
THE FOURTH ENG CO LTD OF CHINA RAILWAYNO 20 BUREAU GRP
View PDF8 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The purpose of the present invention is to solve the problem that the existing underground street passage and the safety of the shield machine cannot be guaranteed when the shield tunnel passes through the existing underground passageway in the prior art, and a shield tunneling tunnel under the ground is proposed. Reinforcement method of crossing passage

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Reinforcing method for shield underneath passing through underground street crossing channel
  • Reinforcing method for shield underneath passing through underground street crossing channel
  • Reinforcing method for shield underneath passing through underground street crossing channel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0030] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention.

[0031] refer to Figure 1-7 It shows a schematic structural view of multiple embodiments of the present invention, and specifically shows the structure of each embodiment. The present invention relates to a reinforcement method for a shield passing through an underground passageway, comprising the following steps:

[0032] A. Destroy the underground passage. The existing interior decoration of the existing underground crossing passage is destroyed, and the steel support is erected in the existing passage by the method of section construction. The length of each section is 1.5m. The steel support erected is frame-shaped, and φ609mm is selected. Steel pipe with wall th...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a reinforcing method for shield underneath passing through an underground street crossing channel, and relates to the technical field of underground street crossing channel reinforcing. The reinforcing method aims to solve the problem that in the prior art, when a shield underneath passes through an existing underground street crossing channel, the safety of the existing underground street crossing channel and a shield tunneling machine during working cannot be guaranteed. According to the technical scheme, the method comprises the following steps that A, a steel support is erected in the existing channel by adopting a sectional construction method; B, grouting is carried out from the existing street crossing channel to the lower part, and a soil body through whichthe shield is about to pass is pre-reinforced; C, synchronous grouting control of the shield tunneling machine is conducted when the shield tunneling machine passes; and D, after the tail of the shield tunneling machine passes through the channel, grouting reinforcement is conducted again. According to the reinforcing method, by means of steel supporting, pre-reinforcement, synchronous grouting and re-grouting after shield tunneling, an existing underground channel crossed with a shield tunnel is reinforced, the reinforcing effect is good, the safety of the existing underground channel beforeand after shield tunneling is guaranteed, and meanwhile, a safety channel of the shield tunneling machine during shield tunneling is also guaranteed.

Description

technical field [0001] The invention relates to the technical field of reinforcement of underground street crossing passages, in particular to a reinforcement method for shield tunnels passing through underground street crossing passages. Background technique [0002] In urban shield tunneling, especially when the tunnel passes through the existing underground passageway, the shield machine has to pass under the existing passageway. Since the passageway crosses the shield tunnel, the distance is very close, and the existing street passageway is at the crossroad. At the entrance, there is a large amount of miscellaneous fill, non-original soil, non-compact geology, and easy settlement, which will affect the safe passage of the shield machine and the safety of the existing underground street crossing passage. It is necessary to reinforce the shield area before and after the shield, so we propose a reinforcement method for the shield to pass through the underground passageway. ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E21D11/10E21D9/06E21F16/02C04B28/26
CPCE21D11/105E21D11/107E21D9/0607E21F16/02C04B28/26C04B2111/00724
Inventor 李洪亮张利军肖先赵鹏陈传平何彦荣武子皓李志永韩立斌宋鹏杰边璐玮罗银昌
Owner THE FOURTH ENG CO LTD OF CHINA RAILWAYNO 20 BUREAU GRP