Method for preventing and treating blockage of high-depth draw shaft
A processing method and technology for sliding wells, which are applied in earth-moving drilling, mining equipment, mining equipment, etc., to achieve the effect of reducing processing risks, avoiding damage, and safe processing methods
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1-2
[0034] The present invention provides a kind of high-deep chute clogging prevention and treatment method for high-deep chute clogging frequently occurring and the existing processing method safety risk, see embodiment 1-2 for details (such as Figure 1-2 )
Embodiment 1
[0036] A method for preventing and treating clogging of a high-deep chute, comprising the following steps:
[0037] Step 1: Control the water content of the ore in the chute 1 to be less than 5% and the mass proportion of fine ore to be less than 50%. The method for controlling the mass proportion of water content and fine ore is specifically: classify the ore in the stope according to the blockiness, Measure the water content of each type of ore and the proportion of fine ore mass, calculate the ratio of different types of ore lowering down the chute according to the water content and fine ore quality requirements, and lower down the chute 1 according to the ratio combination.
[0038] For example, it is assumed that the ore in the stope is divided into Class A and Class B. The water content of Class A ore is 4%, and the mass ratio of fine ore is 30%. The water content of Class B ore is 6%, and the mass ratio of fine ore is 60%. %, then the composition of the ore in the drop ...
Embodiment 2
[0054] This embodiment is further optimized on the basis of embodiment 1, specifically:
[0055] The connecting lane 2 in the step 4 is provided with a retaining wall 4 that is cut off from the chute, the retaining wall 4 is a brick structure, and is located at a distance of 0.2 to 0.5 meters from the ventilation lane 3, and the length of the retaining wall 4 is 3.5 meters. The height is 3 meters, and the thickness is 0.5 meters. The retaining wall 4 is provided with a through vent hole, the diameter of the vent hole is 0.5 meters, and the end of the vent hole away from the well wall of the chute 1 is installed with a device for controlling the on-off of the vent hole. Movable cover 5. One side of the movable cover 5 is hinged on the retaining wall 4, and the other side is provided with a locking plate 6, one end of the engaging plate 6 is rotatably mounted on the movable covering 5, and the other end is connected with a handle 7, and the retaining wall 4 A card slot 8 matchi...
PUM
| Property | Measurement | Unit |
|---|---|---|
| Particle size | aaaaa | aaaaa |
Abstract