A technology with existing building and construction methods, applied in construction, building maintenance, building construction, etc., can solve problems such as anti-floating and instability, and achieve efficient construction, small impact on site environment use functions, and small construction area
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0017] as attached figure 1 Shown: a construction method for pressure relief of lead holes in existing buildings, including the following steps:
[0018] S101. Use stainless steel pipes, flanges, and blind plates to prefabricate the bonded pipe 5 for the drainage and pressure relief of the existing building; the production method of the bonded pipe 5 is to use argon arc welding of multiple stainless steel pipes, and its length depends on the building floor. 2 The thickness should be adjusted, but should not be less than 15cm; single-sided welding is used between the welded stainless steel pipe and the chassis of the flange to meet the connection strength requirements; double-sided full welding is used between the stainless steel pipe and the chassis of the flange , need to meet the connection strength and waterproof requirements. Bolts are used between the flange and the blind plate, and a gasket is installed between the two.
[0019] S102. Excavate the pit 1 on the building...