Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Damping and buffering method and device during blasting construction of mine roadway

A buffer device and roadway technology, which is applied in the field of mine shaft engineering, can solve the problems of lack of support strength, long pouring period, large disturbance of surrounding rock, etc., and achieve the effect of highlighting practical significance, fast construction period, and reducing construction period

Pending Publication Date: 2022-06-03
SHANDONG JINLING MINING CO LTD
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Since the buffer layer basically has no supporting strength, it is necessary to attach a reinforcement board that is longer than the buffer layer and can strongly support the surrounding rocks on both sides; the construction is more complicated, and the surrounding rocks are greatly disturbed
However, the existing patents already have many solutions to the problems of complex construction and long pouring period on site. How to properly combine the prefabricated slab technology with mine roadway blasting technology to achieve shock absorption and obtain early warning at the same time is the frontier in this field. research topic

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Damping and buffering method and device during blasting construction of mine roadway
  • Damping and buffering method and device during blasting construction of mine roadway
  • Damping and buffering method and device during blasting construction of mine roadway

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

like figure 1 and figure 2 As shown in the figure, the shock absorption and buffer device during blasting construction of mine roadway according to the present invention includes an upward roadway 1 and an existing roadway 5, a buffer device is installed at the bottom of the upward roadway 1, and a shock isolation arc surface 6 is installed on the top of the existing roadway 5, The vibration effect generated by the blasting point of the upward roadway 1 is transmitted to the existing roadway 5 through the buffer device and the shock isolating arc surface 6, wherein:

The buffer device includes a buffer prefabricated plate 4, a shock-absorbing pad 3 and a reinforced tower plate 2. The buffer prefabricated plate 4 is firmly connected to the foundation at the bottom of the upward roadway 1 by secondary pouring with cement. The shock-absorbing pad 3 includes an anti-skid pad at the bottom. 32. The sealing pad 31 arranged on the edge of the anti-skid pad 32 and the height-adjustin...

Embodiment 2

The specific shock-absorbing and buffering method is given in this embodiment 2.

[0028] like image 3 As shown, the method for shock absorption and buffer device during blasting construction of mine roadway according to the present invention includes the following steps:

S1: Setting of the buffer device: According to the design of the construction organization, a buffer device is laid for the buffer device in the short-range blasting affected area, namely:

S11: Since the space occupied by the buffer prefabricated plate 4 needs to be excavated, the intermediate interlayer surrounding rock needs to be over-excavated. After the leveling treatment, the buffer prefabricated plate 4 is lifted by a tool through the lifting mechanism and dropped into the foundation of the upward roadway 1;

S12: Load the anti-skid pads 32 and the height-adjusting pads 33 on the buffer prefabricated plate 4, lift the reinforcement tray 2 by the lifting mechanism, and drop it onto the buffer prefabr...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a damping and buffering method and device during mine roadway blasting construction, and belongs to the technical field of mine roadway engineering. A buffer device is mounted at the bottom of an ascending roadway, and a shock insulation cambered surface is mounted at the top of an existing roadway; the buffering device comprises a buffering prefabricated plate, a shock pad and a reinforcing tower plate, the buffering prefabricated plate is fixedly connected with a foundation at the bottom of the ascending roadway into a whole through cement by means of secondary pouring, and the shock pad comprises an anti-skid pad located at the bottom, a sealing pad arranged on the edge of the anti-skid pad and a height adjusting pad arranged in the middle of the anti-skid pad. The reinforced tower plate adopts an inclined surface which is gradually lowered from the outer side to the inner side; the shock insulation cambered surface comprises a reinforcing layer and level gauges installed on the two sides of the reinforcing layer. The reinforcing layer comprises a waterproof plate, vibration isolation rubber and a supporting rib net, and the level gauge transmits information of the inclination angle of the existing roadway to the early warning server through optical fibers; the construction period can be shortened; the blasting early warning information is obtained through the level gauge, the whole construction period is shortened, and blasting data are accurate.

Description

technical field [0001] The invention relates to a shock-absorbing and buffering method and device during blasting construction of mine roadways, and belongs to the technical field of mine shaft and roadway engineering. Background technique [0002] For some mines, slope road development is adopted, and it is difficult to avoid upper and lower layers intersecting and overlapping. During the roadway construction process, roadway blasting can easily cause shock to the existing roadway, thereby causing a series of safety accidents. Cooperate with shock-absorbing buffer device for further safety protection. Since the buffer layer basically has no supporting strength, it is also necessary to attach a reinforcement plate that is larger than the length of the buffer layer and can strongly support the surrounding rocks on both sides; the construction is relatively complicated and the surrounding rock is greatly disturbed. However, the existing patents already have many solutions to ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E21D11/00E21D11/08E21D11/38E21D11/10E21F17/18E21D9/00
CPCE21D11/00E21D11/08E21D11/385E21D11/105E21D11/10E21F17/18E21D9/006Y02A30/60
Inventor 张兴旺姚栋马金宝徐祥熙杨林章魏超张文正邢元猛邵明国傅骁斐
Owner SHANDONG JINLING MINING CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products