Construction method of flanging one-time pouring forming formwork
A construction method and flanging technology, which is applied in the processing of building materials, formwork/formwork/work frame, and on-site preparation of building components. problems, achieve quick installation, simple device structure, and improve construction efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] A kind of construction method of flanging one-time pouring and forming supporting formwork is characterized in that comprising the following steps:
[0041] 1) Prefabricated support 11: Use the residual material after pouring concrete on site, pour it in a rubber mold, insert a plastic sleeve 111 before the final setting of the concrete, the top of the plastic sleeve 111 is flush with the upper end surface of the support 11, and then Place in a curing room with a temperature of 20±2°C and a humidity of ≥95% for 28 days and then demould. The support 11 is a 5cm*5cm*5cm precast concrete block, and the height of the plastic sleeve 111 is 4cm;
[0042] 2) Pay-off positioning: according to the main structure axis of the flanging part and the architectural design drawings, locate and mark each corner of the flanging, and use the ink fountain line to pop out the positioning line on the bottom mold of the main structure;
[0043] 3) Install the support 11: According to the posi...