High-dense emulsified asphalt and preparation method thereof
A technology of emulsified asphalt and asphalt, which is applied to building components, building insulation materials, buildings, etc., can solve the problems of diluting with water, increasing production costs, and inability to use, so as to shorten the preparation time, simplify the production process, and reduce production costs. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0030] Taking the production of high-concentration emulsified asphalt product 100kg of the present invention as an example, the raw materials used and the proportioning thereof are:
[0031] Bitumen 72kg
[0032] JY-R2S type split cationic asphalt emulsifier 2.2kg
[0033] Water 25.8kg.
[0034] The above pitch has a penetration of 101 at 25°C, measured in 0.1 mm.
[0035] Its preparation method is as follows:
[0036] Heat the asphalt to 120°C, add the JY-R2S type medium cracked cationic asphalt emulsifier into 65°C water and stir to dissolve into an emulsifier aqueous solution, add the emulsifier aqueous solution to the colloid mill, and then add the total amount of asphalt at a temperature of 120°C 80% is added to the colloid mill, emulsified for 1-2 minutes to make an emulsion, the emulsion and the remaining asphalt are added to a high-speed shearing machine, and sheared for 2-3 minutes to prepare high-concentration emulsified asphalt.
Embodiment 2
[0038] Taking the production of high-concentration emulsified asphalt product 100kg of the present invention as an example, the raw materials used and the proportioning thereof are:
[0039] Asphalt 63.0kg
[0040] JY-R2S type split cationic asphalt emulsifier 1.0kg
[0041] 36kg of water.
[0042] The penetration of pitch is the same as in Example 1.
[0043] Its preparation method is as follows:
[0044] Heat the asphalt to 110°C, add JY-R2S type medium cracked cationic asphalt emulsifier into 70°C water and stir to dissolve into an emulsifier aqueous solution, add the emulsifier aqueous solution to the colloid mill, and then add 85% of the total amount of asphalt at a temperature of 110°C % into the colloid mill, emulsified for 1 to 2 minutes to make an emulsion, and the emulsion and the remaining asphalt were added to a high-speed shearing machine, and sheared for 2 to 3 minutes to prepare high-concentration emulsified asphalt.
Embodiment 3
[0046]Taking the production of high-concentration emulsified asphalt product 100kg of the present invention as an example, the raw materials used and the proportioning thereof are:
[0047] Asphalt 80.0kg
[0048] JY-R2S type split cationic asphalt emulsifier 3.0kg
[0049] Water 17.0kg.
[0050] The penetration of pitch is the same as in Example 1.
[0051] Its preparation method is as follows:
[0052] Heat the asphalt to 130°C, add the JY-R2S type medium cracked cationic asphalt emulsifier into 60°C water and stir to dissolve into an emulsifier aqueous solution, add the emulsifier aqueous solution to the colloid mill, and then add the total amount of asphalt at a temperature of 130°C Add 75% to the colloid mill, emulsify for 1-2 minutes to make an emulsion, add the emulsion and the remaining asphalt to a high-speed shearing machine, and shear for 2-3 minutes to prepare high-concentration emulsified asphalt.
PUM
Property | Measurement | Unit |
---|---|---|
penetration | aaaaa | aaaaa |
penetration | aaaaa | aaaaa |
penetration | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com