Construction method of buried depth monitoring instrument poreforming and anchorage cable poreforming under unfavorable geological condition
A technology of geological conditions and construction methods, applied in drilling equipment and methods, earthwork drilling, installation of bolts, etc., can solve problems such as difficulties and poor burial depth monitoring instruments to form holes, and achieve huge economic effects.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0017] Embodiment 1. This embodiment is suitable for forming holes in rock masses with smaller cracks.
[0018] When constructing the anchor cable hole 2 on the rock mass 1 with serious geological defects, if the drill bit is stuck and it is difficult to drill in, the drill should not be forced to drill, which will often result in a waste hole because the drill bit is completely stuck and cannot be taken out. , you should stop in time, and then carry out lining grouting for this section of the anchor cable hole. The specific steps are:
[0019] 1) Cut the flexible material, such as color striped cloth or kraft paper on the construction site, into a width of about 4 / 5 of the circumference of the hole, and then grow into a long strip 5 of the depth of the hole, and then cut the long strip One end of the plug is folded into a hat-shaped plug, which can be filled into a three-dimensional shape with paper or cement bags to keep it from collapsing after entering the hole;
[0020] ...
Embodiment 2
[0024] Embodiment 2. This embodiment is suitable for forming holes in rock masses with cracks wider than 4 cm.
[0025] In actual construction, the geological conditions of the rock mass are very poor, and the cracks are wide and deep. For example, when the cracks 2-1 of the rock mass 1 are greater than 4cm, in this case, the method of bridging and grouting at the large cracks can be adopted. Solve, so as not to cause the injected mortar to press the flexible strip into the crack due to insufficient bearing capacity (even make the entire strip fall into the crack under pressure), the specific steps are:
[0026] 1) Flexible materials, such as colored striped cloth or kraft paper at the construction site, can be cut into strips with a width greater than 20-30cm of the anchor cable hole perimeter, and then connected into long strips 5 that meet the hole depth requirements;
[0027] 2) Use the probe 4 with a 60° arc head or an inverted L-shaped probe to find out the specific posi...