Construction method for dismantling prestressed rigid diagonal member of cable-stayed bridge

A construction method and cable-stayed rod technology, which are applied in building maintenance, construction, building construction, etc., can solve problems such as the inability to effectively release the prestress of the rigid cable-stayed rod, the inability to guarantee construction safety, and the small construction surface of construction machinery. The effect of compact construction process, short construction period and low construction cost

Active Publication Date: 2013-09-18
CHINA RAILWAY SIXTH GRP CO LTD +2
View PDF3 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, whether it is directly removed from the anchor nodes at the upper and lower ends of the rigid diagonal stay or directly cut off from the lower end of the rigid diagonal stay, the prestress in the rigid diagonal stay cannot be effectively released, and the rigid diagonal stay will gradually sag after the lower part is cut off. Close to the bridge tower, at this time, the concrete layer on the upper part of the rigid diagonal stay will fall off due to the extrusion of the bridge tower, so the construction safety cannot be guaranteed
However, if the method of directly removing the rigid diagonal tie rods section by section is used, the construction area of ​​the construction machinery will be small and the efficiency will be low.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for dismantling prestressed rigid diagonal member of cable-stayed bridge
  • Construction method for dismantling prestressed rigid diagonal member of cable-stayed bridge
  • Construction method for dismantling prestressed rigid diagonal member of cable-stayed bridge

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0012] The construction method for removing the prestressed rigid cable-stayed rods of a cable-stayed bridge provided by the present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0013] Such as Figure 1-Figure 5 As shown, the construction method of removing the prestressed rigid cable-stayed rod of cable-stayed bridge provided by the invention comprises the following steps carried out in order:

[0014] 1) Peel off the 1-1.5 meter outsourcing concrete layer 3 at the upper end of the rigid diagonal stay 1, and retain the prestressed steel beam 4 at this position;

[0015] 2) Remove the anchor node at the lower part of the rigid diagonal stay rod 1, and gradually shorten the rigid diagonal stay rod 1 from the lower end of the rigid diagonal stay rod 1;

[0016] 3) When the length of the rigid diagonal stay rod 1 is shortened to less than the height of the anchorage point at its upper end from the main girde...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for dismantling a prestressed rigid diagonal member of a cable-stayed bridge. The method comprises the following steps of: stripping a section of a surrounding concrete layer from the upper end of the rigid diagonal member, and retaining the prestressed steel bundle at the part; dismantling the anchoring nodes at the lower part of the rigid diagonal member, and gradually shortening the rigid diagonal member from the lower end of the rigid diagonal member; gradually drooping the rigid diagonal member and attaching to the side surface of a bridge tower; and enabling the bridge tower to fall down toward the other side, wherein the rigid diagonal member falls down together with the bridge tower. The construction method disclosed by the invention has high safety; as the concrete layer in contact with the bridge tower can be removed in advance, the drop of the concrete layer is avoided in the dismantling process; as the prestress in the rigid diagonal member is effectively released by shortening the rigid diagonal member, the construction safety can be ensured; the construction method is economical; as the difficulty in dismantling the rigid diagonal member is shifted to the bridge tower which can be dismantled more easily, the construction cost is low, the operability is high, and the operation is simple and convenient; and moreover, the practicability is strong, the construction process is compact and the construction period is short.

Description

technical field [0001] The invention belongs to the technical field of bridge demolition construction, in particular to a construction method for demolishing prestressed rigid cable-stayed rods of a cable-stayed bridge. Background technique [0002] Cable-stayed bridge, also known as cable-stayed bridge, is a bridge in which the main girder is directly pulled on the bridge tower with multiple prestressed rigid cable-stayed rods. A structural system composed of beams and bodies. Among them, the rigid diagonal stay rod is composed of high-strength prestressed steel beams wrapped with concrete layers, and the two ends are respectively anchored on the main girder and bridge tower. When the cable-stayed bridge cannot meet the requirements of use, it needs to be dismantled. One of the commonly used demolition methods is the non-blasting method. When dismantling cable-stayed bridges by non-blasting methods, especially when dismantling prestressed rigid cable-stayed bridges by no...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E01D24/00
Inventor 李自林贾建国王计良高淑献邢少颖李世宏戴焕民张景立李高王纪龙
Owner CHINA RAILWAY SIXTH GRP CO LTD