Method for manufacturing first layer of steel lining dome of nuclear power station
A manufacturing method and technology for steel lining, which are applied to manufacturing tools, arc welding equipment, welding equipment, etc., can solve the problems of difficulty in guaranteeing the welding quality of the first layer of the dome, low welding efficiency of manual arc welding, etc., so as to improve the welding quality and welding efficiency. Efficiency, quality assurance and production efficiency, the effect of controlling deformation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0013] The manufacturing method of the first layer of the steel-lined dome of the nuclear power plant of the present invention comprises the following steps successively:
[0014] Step 1. According to the design documents and drawing requirements of the first layer of the dome, a tire mold that matches the first layer of the dome wall panel is produced, and the radian requirements and dimensional accuracy of the tire mold are guaranteed, as well as the position of the bisected plate on the tire mold. The splicing weld is not in the suspended position, and it is closely attached to the tire mold;
[0015] The end with the longer arc length of the tire mold is defined as the end A, the end with the shorter arc length of the tire mold is defined as the E end, the outside of the A end is the No. 1 position, and the outside of the E end is the No. 2 position; The projection of the E end on the steel platform is divided into AB, BC, CD and DE segments in sequence;
[0016] Step 2: ...