A time synchronization system and comprehensive automation technology, applied in measuring devices, clocks driven by synchronous motors, synchronization, etc., can solve the problems that cannot satisfy the synchronization and accuracy of multiple remote signaling points, and achieve the accuracy of action time Improve and ensure the effect of accuracy and synchronization
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific Embodiment approach 1
[0026] Specific implementation mode 1: see figure 1 This embodiment is described. A comprehensive automated substation avalanche test device based on a time synchronization system described in this embodiment includes an external clock input unit, a serial communication unit 1, a timekeeping unit 2, an external clock receiving unit 3, and N Pulse output unit 4, main microprocessor unit 5 and clock source selection circuit 6; N is an integer greater than 0,
[0027] The signal output end of the external clock input unit is connected with the clock signal input end of the external clock receiving unit 3; the signal output end of the external clock receiving unit 3 is connected with the first clock signal input end of the clock source selection circuit 6 ,
[0028] The first control signal output end of the main microprocessor unit 5 is connected to the first control signal input end of the clock source selection circuit 6, and the second control signal output end of the main mi...
specific Embodiment approach 2
[0029] Specific implementation two: see figure 2 Describing this embodiment, the difference between this embodiment and the comprehensive automatic substation avalanche testing device based on the time synchronization system described in the first embodiment is that the main microprocessor unit 5 includes a main microprocessor 5-1 , keyboard circuit 5-2, liquid crystal display 5-3, first serial port drive unit 5-4, RS422 bus drive unit 5-6 and LED indication circuit 5-7;
[0030] The first serial port of the main microprocessor 5-1 is connected to the signal input and output end of the first serial port drive unit 5-4, and the RS422 serial communication port of the main microprocessor 5-1 is connected to the RS422 bus drive unit The signal input and output ends of 5-6 are connected, the indicator light control signal output end of the main microprocessor 5-1 is connected with the control signal input end of the LED indication circuit 5-7, and the key signal input end of the m...
specific Embodiment approach 3
[0033] Specific implementation mode three: see figure 1 Illustrating this embodiment, the difference between this embodiment and the time synchronization system-based comprehensive automatic substation avalanche test device described in the first embodiment is that the pulse feedback signal output terminal of the external clock receiving unit 3 outputs the A time synchronization signal containing year, month, day, hour, minute, and second information.