A construction method and insulation layer technology, applied to vertical pipelines, building components, buildings, etc., can solve the problems of wasting refractory materials and refractory mortar, affecting construction progress, and increasing construction costs, so as to shorten the construction period and speed up construction The effect of progress and easy operation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0015] In order to further understand the invention content, characteristics and effects of the present invention, the following examples are given, and detailed descriptions are as follows in conjunction with the accompanying drawings:
[0016] see figure 2 , a concrete flue roof insulation layer construction method, comprising the following steps:
[0017] 1) After the construction of the concrete structure below the top slab is completed, the bottom formwork 7 of the top slab is supported, and the position of the bottom formwork 7 is moved down by one thickness of the insulation layer. After bottom formwork 7 supports are established, clear up the sundry on the bottom formwork 7, and water sawdust is rinsed clean, treats that after water dries, brush release agent on the bottom formwork 7, when preventing demoulding from sticking the refractory spray paint.
[0018] 2) A baffle 1 erected on the inner side of the concrete side wall 9 is supported around the bottom template...
PUM