A brick-like wall made of silicon-aluminum composite material and its preparation process
A silicon-aluminum composite material and a preparation process technology, applied in the field of building boards, can solve the problems of complicated procedures, long construction period, complicated operation, etc., and achieve the effects of good earthquake resistance, good waterproof performance and good effect.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0032] Embodiment 1: preparation imitation green brick wall:
[0033] A preparation process of an imitation blue brick wall made of a silicon-aluminum composite material, comprising the following steps:
[0034] (1) Inject the imitation blue brick pigment into the polymer blended fireproof modified material, silicon-aluminum clinker, and stearic acid, then dry and mix for 20 minutes at 150°; at the same time, put the coal gangue in a high-temperature furnace After being drawn into a fibrous shape according to the standard, it is placed in the imitation green brick mold, and then the mixed material is filled into the imitation green brick mold, and integrated with the coal gangue fiber skeleton.
[0035] (2) Injection molding at a temperature of 150° to form a brick-like wall;
[0036] (3) After forming, open the mold and take out the imitation blue brick wall. When the wall is used as an external wall, the surface is sprayed with anti-ultraviolet material. When it is used as ...
Embodiment 2
[0040] Embodiment 2: prepare imitation red brick wall body:
[0041] A preparation process for imitating red brick walls made of silicon-aluminum composite materials, comprising the following steps:
[0042] (1) Inject the imitation red brick pigment into the polymer blended fireproof modified material, silicon-aluminum clinker and stearic acid, then dry and mix for 20 minutes at 150°; at the same time, put the coal gangue in the high-temperature furnace After being drawn into a fibrous shape according to the standard, it is placed in the imitation red brick mold, and then the mixed material is filled into the imitation red brick mold, and integrated with the coal gangue fiber skeleton.
[0043] (2) Injection molding at a temperature of 150° to form a red brick wall;
[0044] (3) After forming, open the mold and take out the imitation red brick wall. When the wall is used as an external wall, the surface is sprayed with anti-ultraviolet material. When it is used as an indoor ...
Embodiment 3
[0048] Embodiment 3: prepare imitation old brick wall;
[0049] A preparation process for an imitation brick wall made of silicon-aluminum composite material, comprising the following steps:
[0050] (1) Inject the old-fashioned brick pigment into the polymer blended fireproof modified material, silicon-aluminum clinker, and stearic acid, then dry it at 150°, stir and mix it for 20 minutes; at the same time, put the coal gangue in a high-temperature furnace After being drawn into a fiber shape according to the standard, it is placed in the imitation brick mold, and then the mixed material is filled into the imitation brick mold, and it is integrated with the gangue fiber skeleton.
[0051] (2) Injection molding at a temperature of 150° to form an imitation brick wall;
[0052] (3) After forming, open the mold and take out the old-fashioned brick wall. When the wall is used as an external wall, the surface is sprayed with anti-ultraviolet material. When it is used as an indoor...