Low temperature and high turbidity water intake water dredging and antifreezing system and method
An anti-freezing system and high turbidity technology, applied in water supply installations, drinking water installations, sedimentation tanks, etc., can solve the problems of increased turbidity of raw water, inconvenient dredging, and heavy management and maintenance workload, simplifying management, ensuring Water quality, reducing the effect of cement and sand
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0059] Such as figure 1 , 2 As shown, the present embodiment 1 is suitable for the water intake water body 1 is relatively wide, and the water intake water body management department allows the setting of the water intake rectification area 2 in the water body and allows the water intake pump room to be used under the situation of the water intake water body 1; In the water body 1, a water inlet and rectification area 2 is set near one side of the bank, and the middle part of the water inlet and rectification area 2 is connected with a water absorption well. The water pump 61 is located in the water intake pump room, the water intake pump room 6 and the power distribution room 7 are jointly built, and is connected with the water absorption well and the water purification plant through the pipeline system, and the water intake pump room 6 is also equipped with a motor, a lifting device, and a walkway , stairs and railings are connected to the suction well through the water inl...
Embodiment 2
[0068] Such as image 3 , 4 As shown, this embodiment is suitable for the water intake water body 1 is relatively wide, and the water intake water body management department does not allow the water intake rectification area 2 to be set in the water body but allows the water intake pump room to be used under the situation of the water intake water body 1; in this embodiment, the described The water inlet rectification area 2 is arranged on the bank close to the water intake water body 1 side and is parallel to the water flow direction of the water intake water body 1; A partition gate 8 is set, and a mud discharge tank 9 is provided on one side of the water intake body 1, and a partition gate 8 is respectively provided at both ends of the mud discharge tank 9; the structure of the water intake well, the water intake pump room 6 and the power distribution room 7 is the same as in Embodiment 1 Same, no more details.
[0069] The form and operation mode of the flushing and suct...
Embodiment 3
[0071] Such as Figure 4 , 5 As shown, this embodiment is applicable to the water intake water body 1 is narrow, the water intake water body management department does not allow the water intake rectification area 2 to be set in the water body and the water intake pump room is not allowed to be used under the situation of the water intake water body 1; In this embodiment, a water inlet rectification area 2 is set on the bank near the water intake water body 1 side. One end of the mud discharge tank 9 is connected with the intake water body 1 and a partition gate 8 is set, and the other end of the water intake rectification area 2 is connected with the water absorption well; The front chamber 31 of the water suction well is transformed into a transitional form of the connecting area, specifically: partition walls 21 are arranged on both sides of the front chamber 31, and a grille 311 is arranged at the water inlet end and connected with the water inlet rectification area 2 at ...