Stratum reinforcement PSC construction method
A construction method and stratum technology, applied in the field of stratum reinforcement PSC construction, can solve the problems that the overall strength has not been substantially improved, and the soil layer has not been improved, so as to achieve good slurry permeability, flexible hole positions for equipment movement, and improve compressive strength Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0055] After the ratio is determined, the formation drainage construction is carried out, and the tunnel drilling machine is used for drilling again. The diameter of the hole formed by the drilling of the drill bit is not less than 40mm. The proportioned chemical slurry is injected into the hole; and the drilling operation in the formation drainage construction step is sequentially carried out from one side of the construction surface to the other side to complete the formation drainage.
[0056] After the formation drainage is completed, the formation reinforcement grouting is carried out. During the formation reinforcement grouting, the tunnel drilling machine needs to be moved to the hole where the formation drainage has been completed, and the drill bit is drilled into the hole again. When the drill bit reaches the bottom of the hole, use double-liquid grouting The hole-filling and reinforcement slurry supply pump of the pump injects the hole-filling and reinforcement slurr...
Embodiment 2
[0060] After the ratio is determined, the formation drainage construction is carried out, and the tunnel drilling machine is used for drilling again. The diameter of the hole formed by the drilling of the drill bit is not less than 40mm. The proportioned chemical slurry is injected into the hole; when the drill bit is lifted upwards, start the hole-filling and strengthening slurry of the double-liquid injection pump to start grouting. As the grouting parameters change, the lifting speed needs to be adjusted according to the grouting flow rate, the grouting amount and the grouting penetration radius. When the grouting amount or the grouting pressure reaches the design value, continue to lift the rod.
[0061] The grouting process needs to strictly control the grouting pressure, and pay close attention to the grouting amount at the same time. When the pressure rises instantaneously or the grout overflows from the hole wall or the cross-section sand layer, the grouting should be s...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com