BIM technology-based temporary water and temporary electricity management method and system

A management method and technology, applied in the field of water and electricity management methods and systems, can solve problems such as waste of resources, low installation efficiency, messy lines, etc., and achieve the effect of not being stable and tidy, high installation efficiency, and neat lines

Inactive Publication Date: 2015-10-07
GUANGDONG WATER & ELECTRICITY EQUIP INSTALLATION CO LTD
View PDF4 Cites 16 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] 1. All kinds of temporary pipelines near water and electricity need to be laid separately, the lines are messy and the installation efficiency is low;
[0005] 2. Most of the various temporary pipelines follow the traditional laying methods such as street yards and steel wire ropes. The laying effect is not ideal, and it is difficult to ens

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • BIM technology-based temporary water and temporary electricity management method and system
  • BIM technology-based temporary water and temporary electricity management method and system
  • BIM technology-based temporary water and temporary electricity management method and system

Examples

Experimental program
Comparison scheme
Effect test

Example Embodiment

[0108] Example one

[0109] Reference Figure 1-5 , The first embodiment of the present invention:

[0110] The implementation process of a water and electricity management method based on BIM technology of the present invention includes:

[0111] (1) Collect related information about water and electricity planning based on the electromechanical model.

[0112] The process can be further subdivided into:

[0113] (1) Model the BIM model of the architectural, structural, and electromechanical majors according to user needs to obtain a three-dimensional model of electromechanical installation;

[0114] (2) Collect and record relevant data according to the three-dimensional model of the mechanical and electrical installation, such as the relative elevation of the decorative ceiling surface in the public area, the relative height of the building decoration masonry wall relative to the civil structure space, the minimum professional overlap position of the construction surface, and the ground...

Example Embodiment

[0132] Example two

[0133] In this embodiment, the application of the BIM system in the construction of the subway near water and electricity is taken as an example to illustrate the actual application of the present invention.

[0134] (1) Application of design drawings

[0135] 1. Three-dimensional proofreading

[0136] BIM model design is a "rehearsal" of the entire waterfront and power supply design. The modeling process is also a comprehensive "three-dimensional proofreading" process. During this process, a large number of hidden problems in the design can be found to improve the overall design Quality, and greatly reduce the input of post-site processing. The three-dimensional proofreading process mainly includes:

[0137] (1) Three-dimensional proofreading of architectural and structural professional models

[0138] The process is mainly through the collaborative link method to close the three-dimensional model of the building and structure. Through the three-dimensional view,...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a BIM technology-based temporary water and temporary electricity management method and system. The method includes: performing temporary water and temporary electricity pre-planning based on BIM, so as to obtain a three-dimensional model of a temporary water and temporary electricity integrated system; performing collision check of a first time and three-dimensional drawing proofreading, so as to obtain a temporary water and temporary electricity three-dimensional design drawing; performing collision check of the second time and interface conversion on the temporary water and temporary electricity three-dimensional design drawing according to construction site environmental information and practical measurement data, and converting the temporary water and temporary electricity three-dimensional design drawing to a temporary water and temporary electricity two-dimensional construction blueprint; performing three-dimensional simulation construction simulation on the BIM corresponding to the temporary water and temporary electricity two-dimensional construction blueprint, so as to obtain a final BIM construction model; and performing construction according to the temporary water and temporary electricity two-dimensional construction blueprint and the final BIM construction model, thereby adopting a method of combined hanging of groove frames to lay temporary water and temporary electricity facilities. The BIM technology-based temporary water and temporary electricity management method provided by the invention has the advantages of being neat, being relatively high in installation efficiency, being stable and being low in cost, and can be widely applied to the field of computer application.

Description

technical field [0001] The invention relates to the field of computer applications, in particular to a BIM technology-based management method and system for water and electricity. Background technique [0002] Building Information Modeling (Building Information Modeling, referred to as BIM) is based on the relevant information data of construction projects as the basis of the model to establish a building model. BIM technology is a digital tool applied to engineering design and construction management. It integrates relevant information of various projects through parametric models, and shares and transmits them in the whole life cycle of project planning, operation and maintenance, so that engineering and technical personnel Correct understanding and efficient response to various building information provide the basis for collaborative work for the design team and all construction entities including the building operation unit, and play an important role in improving produc...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): G06Q10/06G06Q50/06
Inventor 洪毅生霍家栋郭向阳邹东徐永明张华平王颖金辉罗洋陈启生徐腾记叶茂
Owner GUANGDONG WATER & ELECTRICITY EQUIP INSTALLATION CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products