System and method for comprehensive utilization of circuiting water resource of thermal power plant
A technology of water resources and thermal power plants, applied in the field of comprehensive utilization system of circulating water resources in thermal power plants, can solve problems such as energy waste, water resource waste, and failure to meet the maximum water production of equipment
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0027] Embodiment 1: A comprehensive utilization system of circulating water resources in thermal power plants, which includes a high-speed filter 1, a circulating water filter well 2, a circulating water pump 3, a steam turbine device, a circulating water cooling tower 4, a water delivery pump 5 and a water purification device. The steam turbine device includes a steam turbine condenser 6 , a steam turbine oil cooler 7 , a steam turbine air cooler 8 and a mechanical seal cooling device 9 . The water purification device includes an ultrafiltration raw water tank 10, a multi-media filter 11, an ultrafiltration device 12 and a reverse osmosis device 13. The ultrafiltration device 12 is a Norit ultrafiltration device, and the reverse osmosis device 13 adopts Dow anti-pollution reverse osmosis membrane. The water inlet of the high-speed filter 1 is provided with the first dosing pump 14, the water outlet of the high-speed filter 1 is connected with the water inlet pipeline of the ...
Embodiment 2
[0028] Embodiment 2: Utilize embodiment 1 thermal power plant circulating water resources comprehensive utilization system, the thermal power plant circulating water resource comprehensive utilization method of implementation, it comprises the following steps: (1) cooling tower replenishes water; (2) circulating water treatment in cooling tower; (3) ) circulating water purification treatment;
[0029] (1) Cooling tower replenishment: The raw water is drawn out from the pipeline of the water company, filtered by the high-speed filter 1, sent to the circulating water filter well 2, and then supplied to the steam turbine device for heat exchange through the circulating water filter well 2. After heat exchange, the raw water is sent to into the circulating water cooling tower 4; after the raw water with lower temperature is supplemented into the circulating water, the vacuum degree of the steam turbine condenser can be improved, and the power generation capacity of the equipment can ...
Embodiment 3
[0033] Embodiment 3: utilize embodiment 1 thermal power plant circulating water resources comprehensive utilization system, the thermal power plant circulating water resource comprehensive utilization method of implementation, it comprises the following steps: (1) cooling tower replenishment; (2) circulating water treatment in cooling tower; (3) ) circulating water purification treatment;
[0034] (1) Cooling tower replenishment: The raw water is drawn out from the pipeline of the water company, filtered by the high-speed filter 1, sent to the circulating water filter well 2, and then supplied to the steam turbine device for heat exchange through the circulating water filter well 2. After heat exchange, the raw water is sent to into the circulating water cooling tower 4; after the raw water with lower temperature is supplemented into the circulating water, the vacuum degree of the steam turbine condenser can be improved, and the power generation capacity of the equipment can be...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 