The existing technology is divided into two types: prefabricated components and cast-in-place components. Prefabricated components can be produced in a factory, and the cast-in-place structure has integrity; but there is no construction method that can combine the advantages of the two in the prior art

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0016] The present invention will be specifically introduced below in conjunction with specific embodiments.

[0017] The construction method of the prefabricated integral shear wall includes the following steps: Step 1: Locate and place the standard axis, the control axis, the elevation line of the installation floor, and the elevation line of the stairs; Check and adjust the position; step 3: hoist the prefabricated shear wall; step 4: fix and correct the shear wall by erecting adjustable steel pipe diagonal supports; step 5: grout the shear wall; step 6: prefabricated shear wall Binding of steel bars and formwork installation of force wall edge components; Step 7: Arranging vertical temporary support installation and height correction on the floor; Step 8: Hoisting of prefabricated beams, prefabricated floors, prefabricated balcony panels, air-conditioning panels and stairs; Step 9: Stacking Installation of formwork at the bottom of the floor slab joint; Step 10: pipeline l...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a prefabricated integrated shear wall construction method. The method includes following steps: step 1, positioning and placing a standard axial line and a control axial line, and mounting an elevation line of a floor and an elevation line of a staircase; step 2, adopting a positioning control steel plate to check and adjust position of reserved joint bars; step 3, hoisting a prefabricated shear wall; step 4, fixing and correcting the shear wall by setting up an adjustable steel pipe sway brace; step 5, grouting the shear wall; step 6, performing edge component rebar binding and formwork mounting on the prefabricated shear wall; step 7, arranging a temporary support on the floor, and correcting height; step 8, hoisting prefabricated beams, prefabricated floorboards, prefabricated balcony boards, air conditioner boards and the staircase; step 9, overlapping splicing beams of the floorboards, and mounting a bottom formwork; step 10, laying pipelines; step 11, binding rebars of a cast-in-place layer; step 12, pouring concrete. The prefabricated integrated shear wall construction method has the advantages of high construction efficiency and high integrity.

Description

technical field [0001] A construction method, in particular a shear wall construction method. Background technique [0002] Building industrialization is a green building reform method vigorously promoted by the country at present. Building components are produced in a factory in an assembly line and transported to the site for assembly. This can not only save a lot of labor, but also reduce construction waste on the construction site and improve the construction site and surrounding environment. The existing technology is divided into two types: prefabricated components and cast-in-place components. Prefabricated components can be produced in a factory, and the cast-in-place structure has integrity; however, there is no construction method that can combine the advantages of the two in the prior art. Contents of the invention [0003] In order to solve the deficiencies of the prior art, the purpose of the present invention is to provide a partly prefabricated, partly cast-...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E04B2/56E04G21/00
CPCE04B2/56E04G21/00
Inventor 陈耀钢张军徐鹤松陈俊
Owner NANTONG CONSTR PROJECT GENERAL CONTRACTING
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products