Prefabricated integrated shear wall construction method
A technology of prefabricated assembly and construction method, applied in the direction of walls, building components, buildings, etc., can solve problems such as non-occurrence
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0016] The present invention will be specifically introduced below in conjunction with specific embodiments.
[0017] The construction method of the prefabricated integral shear wall includes the following steps: Step 1: Locate and place the standard axis, the control axis, the elevation line of the installation floor, and the elevation line of the stairs; Check and adjust the position; step 3: hoist the prefabricated shear wall; step 4: fix and correct the shear wall by erecting adjustable steel pipe diagonal supports; step 5: grout the shear wall; step 6: prefabricated shear wall Binding of steel bars and formwork installation of force wall edge components; Step 7: Arranging vertical temporary support installation and height correction on the floor; Step 8: Hoisting of prefabricated beams, prefabricated floors, prefabricated balcony panels, air-conditioning panels and stairs; Step 9: Stacking Installation of formwork at the bottom of the floor slab joint; Step 10: pipeline l...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com