Construction method for large-span pipe corridor pipeline

A construction method and large-span technology, applied in the processing of building materials, construction, building construction, etc., can solve the problems of long straight-line distance for pipeline installation, limited crane working surface and space, and reduced crane use efficiency, etc., to achieve Reduce construction costs and unsafe factors, reduce displacement, and produce simple effects

Active Publication Date: 2016-08-24
CHINA MCC17 GRP
View PDF4 Cites 10 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] At present, due to the long straight-line distance of pipeline installation, within the allowable range of the selected hoisting mechanical performance, frequent shifting is required in the construction area to meet the hoisting conditions, thereby reducing the efficiency of the crane and increasing the cost of the machine; moreover, in some areas Affected by the surrounding environment, the working surface and space of the crane are limited, which brings many unfavorable and unsafe factors to personnel operations

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for large-span pipe corridor pipeline
  • Construction method for large-span pipe corridor pipeline

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0019] The preferred modes of the present invention will be described in further detail below in conjunction with the embodiments.

[0020] A construction method for a large-span pipe gallery pipeline, comprising the following steps:

[0021] S1. Manufacture and install the pipeline welding protective shed 1, assemble and weld the frame 11 with channel steel, make the protective shed skeleton 12 with square steel on the top, and cover the outside of the skeleton 12 with a lightweight three-proof cloth to obtain the pipeline welding protection Shed 1.

[0022] S2. Install two pulley blocks 2 on the pipe gallery truss column, one of the pulley blocks 2 is higher than the height of the pipeline section to be installed, and the two pulley blocks 2 are installed on the same pipe gallery truss column 5 and are located in the pipe gallery truss column 5 On the same side of the pipeline, the first section 6 of the pipeline is paired on the ground, and the length of the pipeline secti...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method for a large-span pipe corridor pipeline. The method comprises the following steps of: S1, manufacturing and installing a pipeline installation and welding protective shed; S2, installing two pulley blocks on pipe corridor truss columns, pairing pipeline segments 1 on the ground, wherein the length of the pipeline segments is greater than the distance between two adjacent pipeline support truss columns; S3, connecting a winch and a whole-pavement hydraulic crane with two sends of the pipeline segments 1 by virtue of steel wire ropes; S4, hoisting the pipeline segments 1 into proper positions on pipeline brackets by virtue of combination of the winch and the whole-pavement hydraulic crane; S5, hoisting the pipeline segments 2 to the pipeline brackets; and S6, welding so as to finish assembled welding of interfaces of the pipeline segments 1 and pipeline segments 2. The construction method for the large-span pipe corridor pipeline is capable of reducing displacement of the crane and increasing the use efficiency of the crane, not only is simple to manufacture, convenient to operate and high in applicability, but also is capable of reducing the construction cost and unsafe factors and ensuring the construction quality and safety.

Description

technical field [0001] The invention belongs to the field of pipeline construction, in particular to a construction method of a large-span pipe gallery pipeline. Background technique [0002] At present, due to the long straight-line installation distance of pipelines, within the allowable range of the selected hoisting machinery performance, frequent shifting is required in the construction area to meet the hoisting conditions, thereby reducing the use efficiency of the crane and increasing the cost of mechanical use; in addition, in some areas, Affected by the surrounding environment, the crane operating surface and space are limited, which brings many unfavorable and unsafe factors to personnel operation. SUMMARY OF THE INVENTION [0003] The purpose of the present invention is to provide a construction method for large-span pipe gallery pipes, so as to solve the problems raised in the above background technology. [0004] To achieve the above object, the present inven...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E04G21/14
CPCE04G21/14
Inventor 胡巍
Owner CHINA MCC17 GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products