Unlock instant, AI-driven research and patent intelligence for your innovation.

Inverted-installation construction method for large pressure steel pipe in high shaft

A pressure steel pipe and construction method technology, applied in water conservancy projects, hydroelectric power generation, hydropower stations, etc., can solve problems such as forced shutdown, unacceptable engineering economics, increased engineering costs, etc., and achieve the effect of easy operation

Inactive Publication Date: 2017-08-15
CHINA GEZHOUBA GROUP CO LTD
View PDF4 Cites 11 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] However, this construction method also has obvious deficiencies and problems: firstly, due to reasons such as engineering technology and cost, the design of diversion tunnels in water conservancy and hydropower projects is mostly buried, and open shafts are rarely used. Engineering applications are often limited by the cross-section and traffic conditions of the diversion tunnel or construction branch tunnel on the upstream side of the shaft, which cannot meet the transportation of large penstocks in the tunnel, or must carry out necessary expansion or treatment, especially when the diversion tunnel is long or When the axis is arranged with steps or small-angle broken lines or the burial depth is large, the increased amount of tunnel expansion and concrete backfilling is very large, and it is often difficult to accept the project economically.
Secondly, in order to meet the hoisting and hoisting requirements of large penstocks in the shaft, special gantry hoisting equipment must be installed on the top of the shaft for open shafts, and the top of the shaft must be expanded and concrete rock anchor beams must be added for buried shafts. processing to meet the layout of large-scale penstock hoisting equipment in the vertical shaft and the demand for hoisting space, and additional engineering costs will be added
In addition, for buried shafts, when the construction period of the concrete lining construction of the civil diversion tunnel overlaps or intersects with the installation and construction period of the shaft penstock, the penstock transportation channel is often occupied by the civil construction, resulting in the failure of construction or forced shutdown of the penstock
Especially when the diversion tunnel is long and there is no special penstock for transporting branch tunnels or the construction period is tight, the contradiction between the penstock installation of the vertical shaft and the construction of the civil tunnel construction becomes more prominent, and sometimes it cannot be overcome and resolved, which seriously affects the project. overall construction progress

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Inverted-installation construction method for large pressure steel pipe in high shaft
  • Inverted-installation construction method for large pressure steel pipe in high shaft
  • Inverted-installation construction method for large pressure steel pipe in high shaft

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0041] Such as figure 1 Among them, a method for inverting large-scale penstock steel pipes in a high shaft, which is characterized in that it includes the following steps: setting a temporary hoisting and hoisting work platform 3 on the top of the penstock installation part in the shaft, and setting a hoist on the temporary hoisting and hoisting work platform 3 2. Use the winch 2 to install the penstock "from top to bottom".

Embodiment 2

[0043] On the basis of embodiment 1, the following steps are also included:

[0044] 1) Select the location of the temporary hoisting and hoisting working platform 3 in the shaft and carry out the installation and construction of the hoisting and hoisting working platform 3;

[0045] 2) Carry out the hoisting, positioning and reinforcement of the initial installation section 6, the second section and the third section of the penstock;

[0046] 3) Concrete backfill construction on the outer wall of the steel pipe;

[0047] 4) Repeat steps 2)-3) to complete the installation and construction of the subsequent penstocks in sequence;

[0048] 5) Carry out paint repainting on the inner wall of the steel pipe;

[0049] 6) Dismantle the hoisting work platform 3 and the completion acceptance of the penstock.

[0050] In a preferred scheme, the step 1) specifically includes the following steps:

[0051] 1) Carry out the construction and reinforcement of the support foundation of the...

Embodiment 3

[0055]1. Selection of the position of the hoisting work platform:

[0056] The selection of the height position of the hoisting work platform in the shaft shall be based on the installation elevation of the upper nozzle of the penstock steel pipe in the shaft, and the upper limit hoisting height position of the hoisting work platform and hoisting hoist, as well as the pressure The requirements for height and space for hoisting and hoisting of steel pipes at the beginning of installation. The formula for calculating the height of the installation base is:

[0057] The installation base elevation of the hoisting working platform (unit: m) = the design elevation of the upper nozzle of the vertical penstock steel pipe at the beginning of installation + the clear height above the upper nozzle of the hoisting rigging at the beginning of installation + the minimum limit working distance of the lifting fixed pulley block + fixed pulley To the base height of the bottom of the hoisting...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to an inverted-installation construction method for a large pressure steel pipe in a high shaft. The inverted-installation construction method comprises the following steps: arranging a temporary hoisting working platform at the top of an installation position of a large pressure steel pipe in a shaft, arranging a hoister on the temporary hoisting working platform, and utilizing the hoister to carry out top-down installation of the pressure steel pipe. With the adoption of the inverted-installation construction method for the large pressure steel pipe in the high shaft, the difficulties that the embedded shaft forward erection construction method cannot realize top-down hoisting from the top of the shaft or transporting of the large pressure steel pipe from the upstream side diversion tunnel are effectively solved, civil construction and expanding excavation are reduced or avoided, the contradiction between the installation of the large pressure steel pipe and the civil construction of the upstream side diversion tunnel is avoided, the engineering construction progress is accelerated, the construction period is shortened, the construction cost is reduced, the installation and construction cost is reduced, and special or large hoisting equipment is not needed.

Description

technical field [0001] The invention relates to the field of hydropower engineering construction, in particular to a method for inverting construction of large pressure steel pipes in high shafts. Background technique [0002] At present, the installation and construction of large-scale penstocks in high shafts of hydropower projects at home and abroad, due to the influence of construction technical conditions and traditional inertial thinking methods, generally adopt "top-down" for hoisting and "bottom-up" for assembly, welding, installation and construction Way (commonly known as: "formal dress method"). This construction method requires that the penstock must be transported from the diversion tunnel on the upstream side or the construction branch tunnel or other temporary roads to the top of the installation site of the penstock in the shaft, and then the penstock shall be placed in sequence using the lifting equipment pre-set on the top of the shaft. They are hoisted se...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02B9/06
CPCE02B9/06Y02E10/20
Inventor 王文忠甘师华邓发江王丽娇陈晓东周杰鲁应华张岩李选卢晓亮
Owner CHINA GEZHOUBA GROUP CO LTD