Inverted-installation construction method for large pressure steel pipe in high shaft
A pressure steel pipe and construction method technology, applied in water conservancy projects, hydroelectric power generation, hydropower stations, etc., can solve problems such as forced shutdown, unacceptable engineering economics, increased engineering costs, etc., and achieve the effect of easy operation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0041] Such as figure 1 Among them, a method for inverting large-scale penstock steel pipes in a high shaft, which is characterized in that it includes the following steps: setting a temporary hoisting and hoisting work platform 3 on the top of the penstock installation part in the shaft, and setting a hoist on the temporary hoisting and hoisting work platform 3 2. Use the winch 2 to install the penstock "from top to bottom".
Embodiment 2
[0043] On the basis of embodiment 1, the following steps are also included:
[0044] 1) Select the location of the temporary hoisting and hoisting working platform 3 in the shaft and carry out the installation and construction of the hoisting and hoisting working platform 3;
[0045] 2) Carry out the hoisting, positioning and reinforcement of the initial installation section 6, the second section and the third section of the penstock;
[0046] 3) Concrete backfill construction on the outer wall of the steel pipe;
[0047] 4) Repeat steps 2)-3) to complete the installation and construction of the subsequent penstocks in sequence;
[0048] 5) Carry out paint repainting on the inner wall of the steel pipe;
[0049] 6) Dismantle the hoisting work platform 3 and the completion acceptance of the penstock.
[0050] In a preferred scheme, the step 1) specifically includes the following steps:
[0051] 1) Carry out the construction and reinforcement of the support foundation of the...
Embodiment 3
[0055]1. Selection of the position of the hoisting work platform:
[0056] The selection of the height position of the hoisting work platform in the shaft shall be based on the installation elevation of the upper nozzle of the penstock steel pipe in the shaft, and the upper limit hoisting height position of the hoisting work platform and hoisting hoist, as well as the pressure The requirements for height and space for hoisting and hoisting of steel pipes at the beginning of installation. The formula for calculating the height of the installation base is:
[0057] The installation base elevation of the hoisting working platform (unit: m) = the design elevation of the upper nozzle of the vertical penstock steel pipe at the beginning of installation + the clear height above the upper nozzle of the hoisting rigging at the beginning of installation + the minimum limit working distance of the lifting fixed pulley block + fixed pulley To the base height of the bottom of the hoisting...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 


