High-efficiency honeycomb type pile head breaking construction process
A construction technology and high-efficiency technology, applied in sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of high construction cost and low construction efficiency, and achieve the effect of preventing dust flying, high construction efficiency and reducing investment.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0014] The high-efficiency honeycomb method broken pile head construction technology includes the following steps:
[0015] Step 1: Make the Reinforcement Cage
[0016] When the steel cage is manufactured, the pile head goes deep into each main reinforcement and the acoustic tube in the tie beam. The isolation sleeve is a soft foam tube to ensure the gap between the pile head steel bar and the poured concrete and the pile head. There is no bond and a certain space between the acoustic tube and the poured concrete.
[0017] Step 2: pouring cast-in-place piles
[0018] After the drilling is completed, the reinforcement cage is put into the borehole, and concrete is poured into the borehole, and the cast-in-place pile is formed after a period of time.
[0019] Step 3: Excavate the Foundation Pit
[0020] Seven days after pouring the concrete, the foundation pit was excavated, and the slope repair and bottom cleaning of the foundation pit were carried out manually. When excava...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com