Backfill earth construction method by using premixed flow state solidified earth
A technology of solidifying soil and backfilling soil, which is applied in filling, soil protection, infrastructure engineering, etc., and can solve problems such as poor control of the amount of rubber soil and ground subsidence
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
example 2
[0022] Construction example 2, in a pipe gallery project, the buried depth is 18 meters, the slopes on both sides are sprayed with concrete slope protection, and the cushion at the bottom of the pipe gallery protrudes to connect with the slope protection on both sides. Clean up the fertilizer tank, use the soil excavated from the pipe gallery as the material for backfilling the ready-mixed fluid solidified soil, and transport it to the horizontal mixer with a conveyor belt, prepare the curing agent into a slurry and transport it to the mixer, the amount of curing agent added It is 22% of the weight ratio of the final product; after adding the curing agent slurry, it is fully mixed, and the crushing device of the mixer breaks the earthwork and fully stirs to form a ready-mixed fluid solidified soil. The ready-mixed fluid solidified soil is poured into the fertilizer tank through the chute, and the fluid solidified soil is poured on both sides of the pipe gallery at the same time...
example 3
[0023] Construction example 3, a coal mine goaf, the roadway is buried 15 meters deep, the maximum width is 5 meters, and the height is 2.5 meters. Convey the earthwork to the vertical mixer, and at the same time, prepare the curing agent into a slurry and send it to the mixer. The amount of curing agent added is 14% of the weight ratio of the final product; after adding the curing agent slurry, it is fully mixed, and the crushing device of the mixer will crush the earthwork. Crushed and fully stirred to form ready-mixed fluid solidified soil. Connect the ground pump to the discharge port of the mixer, and send the fluidized solidified soil into the gob. The slump of the fluidized solidified soil is 18mm, and the 60-day strength of the ready-mixed fluidized solidified soil is not less than 0.5MPa.
PUM
Property | Measurement | Unit |
---|---|---|
Granularity | aaaaa | aaaaa |
Particle size | aaaaa | aaaaa |
Slump | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com