Prefabricated-building intelligent lifting system based on BIM and virtual reality technology and method

A prefabricated and intelligent technology, applied in the direction of instrument, geometric CAD, calculation, etc., can solve the problems of difficult hoisting, long construction period, complicated installation process, etc., and achieve the effect of improving installation quality and efficiency

Active Publication Date: 2018-07-17
鲁班软件股份有限公司
View PDF7 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Prefabricated concrete structural components have a large dead weight, difficult hoisting, complicated installation procedures, and high precision requirements
At present, the hoisting of prefabricated buildings is mainly based on manual hoisting, and manual hoisting has problems such as high labor intensity, low efficiency, long construction period, and poor hoisting accuracy, which seriously slows down the hoisting of prefabricated buildings. efficiency

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Prefabricated-building intelligent lifting system based on BIM and virtual reality technology and method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0025] The invention provides a prefabricated building intelligent hoisting system based on BIM and virtual reality technology. The system includes a server module, a virtual reality scene production module, a component query and report analysis module, a collision inspection module in a virtual scene, and an intelligent Pathfinding module, construction site information collection virtual simulation module, construction site information collection module, virtual scene update module, virtual simulation module of hoisting process, decision-making module, intelligent control module of hoisting process and multi-platform control unit module; server module and reality Scene production module, component query and report analysis module, construction site information collection module, collision inspection module in virtual scene, intelligent pathfinding module in virtual scene, virtual construction site information collection module, virtual scene update module, virtual simulation of...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a prefabricated-building intelligent lifting system based on BIM and the virtual reality technology and a method. The prefabricated-building intelligent lifting system comprises a server module, a virtual-reality-scene making module, a component querying and statement analysis module, a virtual-scene collision detection module, a virtual-scene intelligent way finding module, a construction-site-information-collection virtual simulation module, a construction-site information collection module, a virtual-scene updating module, a lifting-process virtual simulation module,a decision module, a lifting-process intelligent control module and a multi-platform control unit module; component querying and statement analysis in the construction process in virtual scenes, virtual-scene collision detection and intelligent way finding, construction-site information collection, fabrication-site and fabrication-process virtual simulation and real-time online intelligent control of the whole process of prefabricated-building lifting can be achieved, and the installing quality and efficiency of a prefabricated building can be remarkably improved.

Description

Technical field: [0001] The invention relates to a prefabricated building intelligent hoisting system based on BIM and virtual reality technology and a working method thereof, belonging to the technical field of intelligent buildings. Background technique: [0002] Prefabricated building is a new type of building structure, which conforms to the concept of green building in the whole life process. It responds to the national call for energy conservation, emission reduction and green construction, making the construction industry gradually develop from on-site operations to factory and industrial production. Prefabricated concrete structural components have a large dead weight, difficult hoisting, complex installation procedures, and high precision requirements. At present, the hoisting of prefabricated buildings is mainly based on manual hoisting, and manual hoisting has problems such as high labor intensity, low efficiency, long construction period, and poor hoisting accura...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G06F17/50
CPCG06F30/13G06F30/20
Inventor 陆海燕
Owner 鲁班软件股份有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products