A Pile Foundation Hole Forming Method with Efficient Recycling of Mud
A mud and high-efficiency technology, applied in earthwork drilling, wellbore/well components, construction, etc., can solve problems such as ground damage, difficult treatment, and discharge pollution, so as to reduce the amount of waste mud treatment, avoid waste of water resources, The effect of reducing labor intensity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0030] In order to make the object-technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Apparently, the described embodiments are only some of the embodiments of the present invention, but not all of them. Based on the embodiments of the present invention, all other implementations obtained by persons of ordinary skill in the art without making creative efforts fall within the protection scope of the present invention.
[0031] The technical solution of the present invention will be described in detail below in conjunction with the accompanying drawings.
[0032] A pile foundation hole forming method in which mud can be efficiently recycled. A heightened steel casing 1 is buried on the pile site so that the upper part of the heightened steel casing 1 is exposed to the ground. The dregs and mud mixture communication pipe 2 on the high-section steel casing 1 is discharged to the se...