A quick installation process for the main shaft device of mine friction hoist
A technology of friction hoist and spindle device, which is applied in mine lifting equipment, transportation and packaging, infrastructure engineering, etc. It can solve the problems of delayed mine commissioning, long construction time, and more labor, so as to save crane costs and construction The effect of improving quality and efficiency and reducing labor intensity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0027] The overall installation process of the main shaft device of the friction hoist specifically includes the following steps:
[0028] According to the actual situation on site, pre-construction preparatory work should be carried out in advance: check the foundation, process and manufacture the pay-off frame, and release the wire at the point. Specific installation plan:
[0029] ① Determine the relative position of the equipment base according to the center line of the main shaft, the lifting center line and the design size of the drawing, and then use the level to measure the elevation of each foundation, make a record, and then grind the foundation to measure the foundation elevation of each foundation horn position;
[0030] ②After leveling and aligning the shim iron, use the crane to place the main shaft device as a whole on the foundation plane on which the wedge-shaped shim iron has been arranged, and use the wire pendant on the pay-off rack in the hoist machine roo...
Embodiment 2
[0032] The overall installation of the main shaft device of the floor-standing JKMD3.25×4ZⅢ multi-rope friction hoist in the main shaft of Baiheng Gold Mine, Muping District, Yantai City, the details of the equipment and materials used are shown in Table 1:
[0033] Table 1 Details of equipment and materials used
[0034] serial number name quantity unit 1 car crane 80T 1 set 2 steel wire Φ 0.5mm 2kg 3 level gauge DZS3-1 type 1 4 Theodolite J2-JDE 1 5 Frame level 200mm 2 units 6 saw bow 2 handles
[0035] The installation process specifically includes the following steps:
[0036] 1. Check the basics and set out
[0037] After the civil construction is completed, the construction unit will organize relevant units to conduct acceptance inspection. Check the foundation according to the drawing design requirements, observe whether the foundation size, elevation, and foundation holes meet the design re...