Embodiment 1
[0058] Such as figure 1 As shown, an H-shaped steel beam is installed on the building, and the H-shaped steel beam includes a steel beam web 10, an upper flange 11 installed at the top of the steel beam web 10, and a lower flange installed at the bottom end of the steel beam web 10 12. The entire H-shaped steel beam plays the role of supporting the building.
[0059] Such as Figure 4 As shown, the tuned mass damper 20 is placed in the bearing mechanism, and the bearing mechanism carries the tuned mass damper 20 to install it on the steel beam web 10 through the clamping structure installed symmetrically on the steel beam web 10 .
[0060] Complete the initial fixation, and then proceed to the full fixation. It reduces the difficulty of assembly and ensures the safety and efficiency of construction.
Embodiment 2
[0062] On the basis of Example 1, such as figure 1 As shown, the bearing mechanism includes a base plate 30 and a connecting end plate 32 fixedly installed at one end of the base plate 30, the tuned mass damper 20 is fixedly installed on the base plate 30, and side plates are fixedly installed on both sides of the tuned mass damper 20 on the base plate 30 31.
Embodiment 3
[0064] On the basis of Embodiments 1 and 2, the clamping structure includes a first group of Z-shaped connecting parts and a second group of Z-shaped connecting parts symmetrically arranged on both sides of the steel beam web 10, and the first bearing mechanism is clamped on the first In the slot formed by the group of Z-shaped connecting parts and the web 10 of the steel beam, the second carrying mechanism is locked in the slot formed by the second group of Z-shaped connecting parts and the web 10 of the steel beam.
[0065] Such as figure 1 As shown, the first group of Z-shaped connecting parts includes the first Z-shaped connecting part 40 and the third Z-shaped connecting part 43 arranged up and down, and the second group of Z-shaped connecting parts includes the second Z-shaped connecting part 41 and the third Z-shaped connecting part arranged up and down. Four Z-shaped connectors 44 . The first Z-shaped connector 40 and the second Z-shaped connector 41 are symmetrically...