Drainage construction method of counter-slope tunnel boring machine (TBM) tunneling tunnel

A construction method and tunnel technology, applied in drainage, earthwork drilling, safety devices, etc., can solve problems such as no water to pump, sediment accumulation, serious problems, etc., and achieve the effect of reducing pumping distance, saving costs, and reducing investment

CN110454223AActive Publication Date: 2019-11-15CHINA RAILWAY TUNNEL GROUP CO LTD +1
6 Cites 5 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Publication Date
2019-11-15

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention discloses a drainage construction method of a counter-slope tunnel boring machine (TBM) tunneling tunnel. The drainage construction method of the counter-slope TBM tunneling tunnel aimsto solve the technical problem of water accumulation in the construction of the counter-slope TBM tunneling tunnel. The drainage construction method of the counter-slope TBM tunneling tunnel comprisesthe steps that normal water inflow and maximum water inflow of the tunnel are predicted; water tanks are arranged at intervals in the tunnel, the number and volume of the water tanks are determined based on the maximum water inflow of the tunnel, the slope of a counter-slope and the length of the tunnel; drainage pipelines are arranged between the adjacent water tanks, pump stations are arrangedat each water tank, each pump station is provided with a plurality of water pumps, water in the tunnel is gradually drained to the water tanks through the water pumps, and the water in the tunnel is drained in stages. The water drawing distance is reduced, the investment is reduced, inner diameters and material of the drainage pipelines and types of the water pumps are rationally selected, the requirements of drainage can be met while the cost is saved to the greatest extent. By optimizing the configuration of drainage equipment, the tunnel counter-slope drainage construction efficiency is improved, and the counter-slope drainage construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the technical field of tunnel drainage construction, in particular to a drainage construction method for reverse-slope TBM excavation tunnels. Background technique

[0002] TBM (Tunnel Boring Machine) is a tunnel boring machine, which can realize the construction of long tunnels with complex geographical features and landforms that are difficult to realize by traditional drilling and blasting methods, and can realize parallel and continuous operations in construction procedures such as excavation, support, and slag discharge.

[0003] During the tunnel construction process, the tunnel excavation often has a certain slope. When the tunnel excavation slope is along the slope, natural drainage can be used to achieve the purpose of drainage. However, when the tunnel excavation slope is reverse slope, the geological conditions are complex, the reverse slope tunnel distance is long, the slope is large, the buried depth is large, the ...

Examples

Embodiment 1

[0033] Embodiment 1: For the anti-slope TBM excavation tunnel drainage construction method of a certain project, see the TBM construction section figure 1 , using a Φ8.02m open hard rock roadheader for construction.

[0034] The construction section is located in the downstream of reservoir 1. The construction section of the main tunnel is from No. 3 branch tunnel 101 to 1942m downstream of the extension section 2 of the main tunnel, with a total length of 18.275km. (100m), main engine assembly hole 4 (80m), first deployment hole 5 (200m), first starting hole 6 (25m), TBM first tunneling section 7 (8310m), upstream connection section 8 (1500m), Maintenance hole 9 (60m), second entry hole 10 (240m), downstream connecting section 11 (1500m), second starting hole 12 (25m) and TBM second tunneling section 13 (6235m).

[0035] The horizontal distance of No. 3 branch tunnel 101 is 3872m, the slope distance is 3885m, and the comprehensive slope is 8.18%. In order to solve the probl...

Embodiment 2

[0133] Example 2: Drainage scheme of the branch hole, on the basis of Example 1, drain water through the branch hole.

[0134] Drainage scheme of 2# branch tunnel: add a 300mm drainage pipeline (No. 3) on the basis of the original two 300mm drainage pipelines (No. 1 and No. 2 pipelines, which can only be used after partial treatment) in 2# branch tunnel , No. 1 and No. 2 pipelines are pumped out of the cave with two-stage drainage, and No. 3 is pumped to the top with one pump and directly pumped out of the cave. Pipeline No. 1 is equipped with a MD280-215 water pump at the bottom of the cave to discharge to the original 2# water tank in the 2# branch cave, and a MD280-172 water pump is installed in the original 2# water tank to pump out the cave; No. 2 pipeline is in One set of MD250-151 water pump is installed at the bottom of the cave to pump and discharge to the original 3# water tank of the 2# branch cave, and one set of MD280-172 water pump is installed at the original 3#...