A manufacturing process, copper rod technology, applied in the field of copper rod manufacturing process, can solve the problems of limited heat insulation effect of continuous casting crystallizer, and achieve the effects of accelerating the crystallization rate, improving heat insulation effect, and preventing oxidation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0027] Embodiment one: if figure 1 , figure 2 Shown, the present invention also discloses a kind of manufacturing process of copper rod, comprises the following steps:
[0028] 1) Put the electrolytic copper raw material into a closed mixed molten material furnace for smelting at a melting temperature of 1100-1200°C. After the electrolytic copper is completely melted, continue smelting for 15-20 minutes;
[0029] 2) Transfer the molten material in the closed mixed molten material furnace to the upward continuous casting molten material furnace. The heating temperature of the upward continuous casting molten material furnace is 1080-1100 degrees Celsius; then the molten material enters the continuous casting crystallization through the siphon effect In the continuous casting crystallizer, cooling crystallization is carried out through the cooling water system;
[0030] 3) The crystallized copper rod in the continuous casting crystallizer is drawn out from the top of the cont...
Embodiment 2
[0031] Embodiment two: if figure 1 and figure 2 As shown, the present invention discloses a continuous casting crystallizer, which includes a graphite upper lead pipe 1, an argon heat insulation device 3 and a cooling water device 2, and the bottom end of the graphite upper lead pipe is equipped with a graphite inner pipe 4, The outer peripheral surface of the bottom opening of the graphite upper guide tube is tapered. The outer side of the graphite inner tube is also equipped with a heat insulation sleeve 5, and an annular heat insulation cavity 6 is arranged inside the heat insulation sleeve. The heat exchange coil 9 and the thermal insulation sleeve 10 of the air intake pipeline and the return pipeline, the heat exchange coil is installed in the heat insulation chamber, the air pump 11 is installed on the air intake pipeline, and the top of the air intake pipeline is connected to the insulation Sleeve, the end of the return line is connected to the insulation sleeve; the...