Pre-consolidation-prestress-reinforcement coupled fluid mud solidification pile preparation method and preparation structure
A liquid mud and prestressing technology, which is applied in foundation structure engineering, sheet pile walls, buildings, etc., can solve the problems of low strength of solidified liquid mud, too high curing agent can not be added, and can not meet the requirements of foundation treatment, etc., to achieve Improve the effect of reinforcement and increase the strength
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0042] A kind of pre-consolidation-prestress-reinforcing coupling action fluid mud curing pile preparation method provided by the present invention comprises the following steps:
[0043] The first step: install ten fiber fixing buckles 12 on the circumferential end face of the prefabricated pile tip 2, and fix one end of ten bundles of geotechnical fibers 4 on the fiber fixing buckles 12 respectively;
[0044] The second step: in the tube wall of the immersed tube 1, a number of through fiber holes 3 are provided along the axial direction. The bottom of the immersed tube 1 penetrates to the top of the immersed tube 1, fills the fiber hole 3, and finally protrudes from the top of the immersed tube 1, and the protruding distance is about 50cm;
[0045] Step 3: Press the prefabricated pile tip 2 and the immersed tube 1 into the foundation through the pile driver of the immersed tube 1, the input end of the pump body extends into the hollow structure of the immersed tube 1, start...
Embodiment 2
[0052] A kind of pre-consolidation-prestress-reinforcing coupling action fluid mud curing pile preparation method provided by the present invention comprises the following steps:
[0053] The first step: install ten fiber fixing buckles 12 on the circumferential end face of the prefabricated pile tip 2, and fix one end of ten bundles of geotechnical fibers 4 on the fiber fixing buckles 12 respectively;
[0054] The second step: in the tube wall of the immersed tube 1, a number of through fiber holes 3 are provided along the axial direction. The bottom of the immersed tube 1 penetrates to the top of the immersed tube 1, fills the fiber hole 3, and finally protrudes from the top of the immersed tube 1, and the protruding distance is about 50cm;
[0055] Step 3: Press the prefabricated pile tip 2 and the immersed tube 1 into the foundation through the pile driver of the immersed tube 1, the input end of the pump body extends into the hollow structure of the immersed tube 1, start...
PUM