Construction method for preventing settlement of shield construction crossing building
A construction method and building technology, which are used in earth-moving drilling, wellbore lining, tunnel lining, etc., can solve the problems that cannot meet the requirements of ground settlement of non-foundation houses, damage to houses, and the number of houses that have not been identified in advance and cannot be avoided. problems such as surface subsidence, achieving good social and economic benefits, facilitating practical operations, and ensuring safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] Such as figure 1 As shown, a construction method for shield construction to pass through a building to prevent settlement includes the following steps:
[0041] Step A: Shield machine debugging and accessories installation.
[0042] Step B: preparing grouting grout b.
[0043] Step C: Tunneling and grouting of the shield machine.
[0044] Step D: After the grouting is finished, close the valve.
Embodiment 2
[0046] Such as figure 1 As shown, a construction method for shield construction to pass through a building to prevent settlement includes the following steps:
[0047] Step A1: Clean the reserved radial grouting holes 1 in the upper half of the shield machine precursor.
[0048] Step A2: Install a ball valve in the reserved radial grouting hole 1 in the upper half of the shield machine front body.
[0049] Step A3: Dredge the radial grouting hole to the casing 2 of the shield machine by installing a ball valve.
[0050] Step A4: Install the prefabricated mixer, pressure gauge, slurry release valve and slurry storage tank.
[0051] Step B1: Select a slurry storage tank and a liquid storage tank with a liquid level scale.
[0052] Step B2: Prepare bentonite liquid and superplasticizer and store them in slurry storage tank and liquid storage tank respectively.
[0053] Step B3: Mix the bentonite liquid and superplasticizer to obtain grout b.
[0054] Step B4: Perform a mixin...
Embodiment 3
[0060] Such as figure 1 As shown, a construction method for shield construction to pass through a building to prevent settlement includes the following steps:
[0061] Step A1: Clean the reserved radial grouting holes 1 in the upper half of the shield machine precursor.
[0062] Step A2: Install a ball valve in the reserved radial grouting hole 1 in the upper half of the shield machine front body.
[0063] The step A2 specifically includes: installing a corresponding ball valve at the position of the radial grouting hole of the shield precursor to ensure that the ball valve is intact.
[0064] Step A3: Dredge the radial grouting hole to the casing 2 of the shield machine by installing a ball valve.
[0065] Step A4: Install the prefabricated mixer, pressure gauge, slurry release valve and slurry storage tank.
[0066] By setting up the mixer, it is convenient to mix the bentonite liquid and superplasticizer to ensure uniform mixing.
[0067] The slurry storage tank has sca...