Vacuum dewatering well capable of reutilizing water resources and construction method thereof
A construction method and technology of precipitation wells, which are applied in water conservation, water supply devices, drinking water devices, etc., can solve the problems of increasing water costs at the construction site, easy generation of spring soil, and long precipitation duration
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0032] A vacuum dewatering well that can make water resources secondary use, such as figure 1 and figure 2 As shown, it includes well hole 1, well pipe 2, filter 3, gravel sand layer 4, sealing coating 5, vacuum pump 6 and tertiary sedimentation tank 7; well pipe 2 is centrally placed in well hole 1; filter 3 is placed in the well pipe 2; the gravel sand layer 4 is filled in the gap between the well pipe 2 and the inner wall of the well hole 1; the sealing coating 5 is used to seal the top opening of the well hole 1 and the well pipe 2; the vacuum pump The water inlet of 6 is connected to the well pipe 2 through a pipeline, and the water outlet of the vacuum pump 6 is connected to the three-stage sedimentation tank 7 through a pipeline, and a vacuum is formed in the well hole 1 through the sealing coating 5, and the water in the ground aquifer is accumulated in the ground through the action of pressure. In the well pipe 2, and between the well pipe 2 and the well hole 1, the...
Embodiment 2
[0035] A kind of construction method, its construction flow chart is as follows image 3 Shown, be used for building above-mentioned vacuum dewatering well, construction method comprises the following steps:
[0036] Step 1: Measure and release the well position, and measure and release the well position on the ground according to the layout requirements of the well position;
[0037] Step 2: Drilling. Drilling is carried out on the well site to form a well site hole 1. After the hole is drilled on the foundation, it will reach the bottom. When the drilling construction reaches the design depth, it is advisable to drill 0.3-0.5m more as a reserved space. The space is flooded;
[0038] Step 3: lower the well pipe 2, put the well pipe 2 in the center of the well hole 1, measure the hole depth of the well hole 1 before running the pipe, and start lowering the well pipe 2 after the hole depth meets the design requirements;
[0039] Step 4: Fill the gravel sand, put the gravel sa...