Pre-operation method of LNG ship enclosure system
A technology for LNG ships and sides, which is applied to ships and other directions, can solve problems such as limited space in LNG tanks, material bumps, and hidden quality problems, and achieve the effects of humanized overall layout, high construction fluency, and high production efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0048]Such asFigure 1-15 As shown, this embodiment discloses a pre-operation platform outside the LNG cabin of a membrane type containment system. The pre-operation platform includes a material storage and transportation platform 1, a constant temperature and humidity room 2, and a cabin entry platform 3.
[0049]The material storage and transportation platform 1 is equipped with platform ladders 141 and 142 and a material lifting device 15.
[0050]The top of the material storage and transportation platform 1 is divided into three functional areas: storage work area 1A, passage area 1B, and loading area 1C. The uniform load of the storage work area 1A is not less than 250Kg / m2, the area is not less than 300m2, and the length and width are equal. Not less than 10m, the uniform load of the passage area 1B is not less than 300Kg / m2, the pass width is not less than 4m, the uniform load of the feeding area 1C is not less than 300Kg / m2, and the length and width are not less than 4m.
[0051]The s...
Embodiment 2
[0063]Such asFigure 1-15 As shown, this embodiment discloses a method for pre-operation outside the LNG tank of a membrane-type containment system, which specifically includes the following steps:
[0064]S1: Build the material storage and transportation platform 1 outside the LNG tank A facing the temporary process hole A1, and the height difference between the top of the material storage and transportation platform 1 and the lower mouth of the temporary process hole A1 is not more than 100mm;
[0065]S2, build a constant temperature and humidity room 2 based on the material storage and transportation platform 1;
[0066]S3, install the cabin entry platform 3 based on the material storage and transportation platform 1;
[0067]S4. Install an air conditioning system in the constant temperature and humidity room 2 and adjust the temperature and humidity to the required working environment to form a pre-operation platform for the enclosure system;
[0068]S5: Lift the materials, tools and equipment ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com